CPE Performance Measurement & Reporting Flashcards
6 cards from real CPE practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 6 CPE Performance Measurement & Reporting flashcards as text
In Earned Value Management (EVM), the Cost Variance (CV) is calculated as:
Answer: EV – AC
CV = EV – AC; a positive CV means the work accomplished cost less than budgeted, while a negative CV indicates a cost overrun.
A To-Complete Performance Index (TCPI) greater than 1.0 means:
Answer: The remaining work must be completed more efficiently than past performance to meet the budget goal
TCPI > 1.0 indicates that future work efficiency must exceed historical efficiency to achieve the target EAC or BAC.
Which schedule metric is best used to identify trends in float erosion over time?
Answer: Total Float Trend Analysis plotted period-over-period
Plotting total float of critical and near-critical paths over successive updates reveals whether float is being consumed faster than expected.
A project's Baseline Execution Index (BEI) is used to measure:
Answer: The ratio of activities completed on time vs. those that were planned to be complete
BEI measures schedule execution fidelity by comparing how many activities were completed as planned vs. what the baseline required.
The primary purpose of a project Variance Analysis Report (VAR) is to:
Answer: Document the root cause, impact, and corrective action for significant schedule or cost variances
VARs provide a structured explanation of why variances occurred and what actions will be taken to recover, forming a key control tool.
Which percent-complete measurement method is most objective for construction activities?
Answer: Units completed method — units of work done divided by total units
The units completed method ties percent complete to a countable, verifiable output, minimizing subjectivity in progress reporting.