An S-curve in project cost management is used to represent:
Answer: Cumulative planned and actual costs over time
An S-curve plots cumulative planned value, earned value, and actual cost over time, showing typical slow-start, rapid-mid, and tapering-end cost patterns.
Which technique involves identifying and quantifying the uncertainties in cost estimates using probability distributions?
Answer: Monte Carlo simulation
Monte Carlo simulation runs thousands of iterations using probability distributions for each cost element to produce a range of possible total costs.
A contractor is awarded a Cost-Plus-Incentive-Fee (CPIF) contract. The fee increases when:
Answer: Actual costs are lower than the target cost
In CPIF contracts, the contractor earns a higher fee when actual costs come in below the target cost, incentivizing cost efficiency.
Variance at Completion (VAC) is calculated as:
Answer: BAC - EAC
VAC = BAC - EAC, representing the expected final cost variance (positive = under budget, negative = over budget) at project completion.
Which element of the Work Breakdown Structure (WBS) is typically the lowest level used for cost estimation?
Answer: Work package
Work packages are the lowest WBS level where costs can be reliably estimated, scheduled, and tracked.
A project cost estimate that accounts for price escalation over a multi-year project is called:
Answer: An escalated or inflated estimate
An escalated estimate adjusts future-year costs for expected inflation or price increases over the project duration.
When should a project manager formally request a change to the cost baseline?
Answer: When an approved scope change impacts the project budget
Cost baseline changes require an approved scope change through the integrated change control process; cost overruns alone do not justify re-baselining.