What is the purpose of a test certificate for a new piece of lifting equipment?
Answer: It confirms the equipment has been tested by the manufacturer and is safe for the specified SWL
A test certificate from the manufacturer confirms that the equipment has been load-tested and is safe for use at the specified SWL. It is required before first use and must be kept with the equipment records.
What is a 'load indicator' or 'load moment indicator' (LMI) on a crane?
Answer: A device that warns the operator when the load approaches or exceeds the crane's safe capacity
A load moment indicator (LMI) monitors the load and boom configuration in real time and warns — or stops the crane — when the load approaches the capacity limit for that configuration.
Why is it important to use the correct sling angle when lifting a load?
Answer: The angle affects the tension in each leg of the sling — as angle increases from vertical, tension increases and effective capacity reduces
As the angle between sling legs increases (legs become more horizontal), the tension in each leg increases beyond the weight of the load. At 60 degrees from vertical each leg carries the full load weight, greatly increasing failure risk.
What is a 'lift supervisor' under LOLER and what are their responsibilities?
Answer: A competent person responsible for supervising the lift, ensuring the plan is followed and the area is safe
The lift supervisor is a competent person responsible for supervising the lifting operation, ensuring the lifting plan is followed, the exclusion zone is maintained, and any unsafe conditions are addressed.
What does LOLER say about using construction plant (e.g. a telehandler) for lifting operations?
Answer: It must be suitable for lifting, properly examined, and lifting operations planned by a competent person
LOLER applies fully when construction plant is used for lifting. The equipment must be suitable and thoroughly examined, and the lifting operation must be planned by a competent person.
During a lift, the load begins to swing uncontrollably. What should the operator do?
Answer: Lower the load to the ground in the safest available position and stop the lift
A swinging load is an immediate danger. The safest response is to lower the load to the ground in the nearest safe position and halt the lift. The cause must be investigated before resuming.