← All CPCS Flashcard Decks

Pre-Use Checks Flashcards

6 cards from real CPCS practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 Pre-Use Checks flashcards as text
  1. What is the primary purpose of a pre-use check on construction plant?

    Answer: To identify defects or hazards before operation begins

    Pre-use checks exist to identify any defects, damage, or hazards before the plant is operated, preventing accidents caused by mechanical failure or unsafe conditions.

  2. When should a pre-use check be carried out?

    Answer: Before every work period in which the plant will be used

    A pre-use check must be carried out before every work period — at the start of each shift or whenever the operator takes over the plant — not just periodically.

  3. Which of the following would you check as part of a plant pre-use inspection?

    Answer: Fluid levels, tyres or tracks, lights, controls, and safety devices

    A thorough pre-use check covers fluid levels (fuel, oil, coolant, hydraulic), tyres or tracks, lights, mirrors, controls, alarms, safety devices, and any visible structural damage.

  4. You carry out a pre-use check and find a hydraulic oil leak. What should you do?

    Answer: Take the plant out of service and report it before operating

    A hydraulic oil leak can cause sudden loss of control and is a serious safety defect. The plant must be taken out of service immediately and the defect reported for repair.

  5. What should an operator do if a pre-use check reveals the travel alarm is not working?

    Answer: Take the plant out of service and report the defect

    A travel alarm warns nearby workers of plant movement. Its absence is a significant safety hazard requiring the plant to be taken out of service until the alarm is repaired.

  6. Who is responsible for completing the pre-use check?

    Answer: The operator who will be using the plant

    The operator who will be using the plant is responsible for completing the pre-use check. They are in the best position to notice changes from the previous shift and are accountable for operating the plant safely.