Project Change Management Flashcards
7 cards from real CPC practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Project Change Management flashcards as text
Which of the following inputs is MOST essential when evaluating the impact of a proposed change on the project schedule?
Answer: The schedule baseline
The schedule baseline is the approved version of the project schedule used to measure and compare the impact of any proposed schedule changes.
In change management, what does 'impact analysis' involve?
Answer: Evaluating how a proposed change will affect all project constraints such as scope, time, cost, and quality
Impact analysis is the process of evaluating how a proposed change will affect all aspects of the project, including scope, schedule, cost, quality, and risk.
Who is responsible for submitting a change request?
Answer: Any project stakeholder, including team members, sponsors, or clients
Change requests can be submitted by any project stakeholder, including team members, the project coordinator, the sponsor, clients, or vendors.
A project is experiencing frequent informal scope changes from the client. The BEST approach for the project coordinator is to:
Answer: Reinforce the formal change control process with the client and document all requests
Enforcing the formal change control process ensures all changes are documented, evaluated, and approved before implementation, preventing scope creep.
A rejected change request should be:
Answer: Documented in the change log with the reason for rejection
Even rejected change requests must be documented in the change log with rationale, as they form part of the project's historical record.
Which project management process group is MOST closely associated with Integrated Change Control?
Answer: Monitoring and Controlling
Integrated Change Control is a Monitoring and Controlling process group activity, as it continuously oversees and manages changes throughout the project lifecycle.
What is the relationship between change management and version control in project documentation?
Answer: Version control supports change management by tracking document revisions and maintaining historical records
Version control supports change management by ensuring that each revision of a project document is tracked, making it possible to reference prior versions and maintain integrity.