Project Procurement & Contracts Flashcards
6 cards from real CPC practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 6 Project Procurement & Contracts flashcards as text
Which term describes a vendor's preliminary written statement of capability and approach before a formal proposal is requested?
Answer: Request for Information (RFI)
An RFI gathers market information from vendors early in procurement planning, before the formal solicitation is issued.
A project coordinator receives a vendor invoice that does not match the agreed deliverable milestones. The appropriate action is to:
Answer: Reject the invoice and formally request a corrected invoice aligned to contract terms
Invoices must match contract terms; accepting non-compliant invoices undermines contract integrity and financial controls.
Centralized contracting means:
Answer: A dedicated procurement department manages all contracts across projects
Centralized contracting provides consistent procurement expertise, standardized processes, and stronger negotiating leverage.
Which statement about procurement planning is correct?
Answer: Procurement planning should identify what to procure, when, and how before soliciting vendors
Early procurement planning ensures requirements, timelines, and contracting strategies are defined before the market is engaged.
A holdback (retainage) clause in a contract means:
Answer: A percentage of payment is withheld until final acceptance to ensure completion
Retainage incentivizes vendors to complete and fix all outstanding issues before final payment is released.
When evaluating vendor proposals, a weighted scoring model is preferred because:
Answer: It allows the team to objectively rank proposals against multiple criteria with different levels of importance
Weighted scoring quantifies each evaluation criterion's relative importance, making proposal comparisons transparent and defensible.