Construction Project Management & Planning Flashcards

7 cards from real CPC practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Construction Project Management & Planning flashcards as text
  1. What is 'fast-tracking' in construction project scheduling?

    Answer: Overlapping phases or activities that were originally planned sequentially

    Fast-tracking overlaps activities that would normally be performed in sequence, compressing the schedule by accepting increased risk of rework.

  2. A project manager is preparing the project closeout. Which document summarizes lessons learned, final cost data, and as-built conditions for future reference?

    Answer: Project Closeout Report

    The Project Closeout Report captures lessons learned, final cost and schedule performance, and as-built documentation for use on future projects.

  3. Which type of project estimate is typically prepared from conceptual design documents with an expected accuracy of -15% to +50%?

    Answer: Parametric Estimate

    A parametric estimate uses statistical relationships between historical data and project parameters (e.g., cost per square foot) and is appropriate at the conceptual stage with -15%/+50% accuracy.

  4. An owner inserts a 'no-damage-for-delay' clause in the construction contract. What is the effect of this clause?

    Answer: It limits the contractor's remedy for owner-caused delays to time extensions only, not additional money

    A no-damage-for-delay clause generally limits the contractor's remedy for owner-caused delays to time extensions, barring monetary compensation for delay damages.

  5. Which scheduling relationship allows a successor activity to start a specified period of time after the predecessor activity has started?

    Answer: Start-to-Start (SS) with lag

    A Start-to-Start (SS) relationship with lag means the successor activity cannot start until a defined period after the predecessor has started, commonly used for overlapping activities.

  6. During construction, an owner requests a scope addition that significantly increases the contract value. The contractor should process this through a:

    Answer: Formal Change Order

    A formal Change Order is the proper contract mechanism to document, price, and execute agreed changes to the scope, cost, and/or schedule of a construction contract.

  7. A project manager is comparing two site layout options using a Decision Matrix. What is the key advantage of this tool over informal judgment?

    Answer: It provides a structured, weighted scoring method that reduces bias in multi-criteria decisions

    A Decision Matrix provides a systematic, weighted evaluation of alternatives against multiple criteria, making the decision process transparent and less susceptible to cognitive bias.