Project Management & Collaboration Flashcards
7 cards from real CMA practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 7 Project Management & Collaboration flashcards as text
An architect is preparing a project work plan for an adaptive reuse project. Which factor most significantly influences the phasing strategy?
Answer: Building occupancy requirements during construction and phased operational continuity
Adaptive reuse of occupied buildings requires phasing strategies that maintain building operations and occupant safety throughout the construction process.
What is the significance of substantial completion in construction contract administration?
Answer: It is the date when the work is sufficiently complete for the owner to occupy and use it for its intended purpose
Substantial completion triggers the start of the warranty period, transfer of utilities costs to the owner, and establishes the basis for final payment retainage reduction.
A master architect is assembling a team for a healthcare project requiring highly specialized expertise. What is the most important criterion for selecting subconsultants?
Answer: Demonstrated experience with comparable healthcare facility types and applicable regulatory requirements
Healthcare projects involve complex infection control, code, and operational requirements that demand subconsultants with directly relevant specialized experience.
How should a master architect approach value engineering requests that threaten to compromise the building's long-term performance?
Answer: Evaluate each proposal against life-cycle cost analysis and advise the owner of long-term performance and cost implications
Life-cycle cost analysis quantifies long-term performance implications, enabling informed owner decisions rather than short-term cost decisions that increase total cost of ownership.
Which type of project delivery agreement is MOST appropriate when an owner requires a guaranteed maximum price before design is fully complete?
Answer: Construction management at-risk
A construction manager at-risk provides a guaranteed maximum price (GMP) during design, combining early contractor involvement with cost certainty before full document completion.
When an architect issues a field order during construction, what is the key distinction from a change order?
Answer: A field order directs minor changes within the general scope without adjusting contract sum or time; a change order modifies both
Field orders (or architect's supplemental instructions) address minor clarifications within scope without contract modification, while change orders formally adjust cost and/or schedule.
A master architect is leading a post-occupancy evaluation (POE) for a completed building. What is the primary professional benefit of this activity?
Answer: Identifying performance gaps between design intent and actual building performance to improve future design decisions
POEs create evidence-based feedback loops that improve future design decisions, validate performance assumptions, and strengthen the architect's expertise over time.