During construction administration, a Contractor submits a Request for Information (RFI). The landscape architect's primary obligation is to:
Answer: Respond with clarification within a reasonable time without changing the contract scope
RFIs are requests for clarification; the landscape architect must respond promptly to keep construction on schedule without unilaterally modifying contract scope.
What is the purpose of a 'punch list' in the construction administration phase?
Answer: A record of incomplete or deficient work items that must be corrected before final acceptance
The punch list documents deficiencies or incomplete items identified during a final walk-through that the contractor must correct before substantial or final completion is certified.
Which drainage slope is the minimum typically recommended for paved pedestrian surfaces to ensure positive drainage away from structures?
Answer: 1.0%
A minimum 1.0% slope is generally recommended for paved pedestrian surfaces to achieve positive drainage, though 2% is preferred on asphalt.
A 'submittals log' maintained by the landscape architect during construction administration tracks:
Answer: Shop drawings, product data, and samples sent by the contractor for review
The submittals log records every shop drawing, product data sheet, and sample submitted by the contractor, along with review status and return dates.
In landscape irrigation design, 'precipitation rate' refers to:
Answer: The rate at which a sprinkler system applies water, expressed in inches per hour
Precipitation rate (inches/hour) describes how quickly an irrigation system delivers water to the landscape, critical for matching soil infiltration rates.
Which standard governs accessibility requirements for exterior routes, ramps, and site furniture in U.S. landscape construction documents?
Answer: ADA Standards for Accessible Design / ABA Accessibility Standards
The ADA Standards for Accessible Design and ABA Accessibility Standards govern accessible routes, ramps, parking, and site elements in federally covered construction.
A 'construction contingency' included in a project budget is best described as:
Answer: A reserve fund for unforeseen conditions or scope changes during construction
A construction contingency is a budgetary reserve—typically 5–15% of construction cost—set aside to cover unforeseen field conditions, design changes, or scope adjustments.