What is the minimum safe distance a crane must maintain from energized power lines rated at 50 kV or below?
Answer: 10 feet
OSHA 29 CFR 1926.1408 requires a minimum 10-foot clearance from energized power lines up to 50 kV.
When a crane operator cannot see the load at all times, what must be done?
Answer: Use a signal person
OSHA requires a qualified signal person whenever the operator does not have a clear view of the load or path of travel.
A wire rope used for rigging shows more than __ broken wires in one lay length and must be removed from service.
Answer: 6
Six or more broken wires in one rope lay, or three or more in one strand, is a criterion for removal from service per ASME B30.9.
What document must be available in the cab or on the crane at all times during operations?
Answer: Manufacturer's load chart
OSHA 29 CFR 1926.1417 requires the load chart to be in the cab and legible so operators can verify capacity before any lift.
Which factor does NOT affect a crane's rated load capacity?
Answer: Operator's years of experience
Rated capacity is a mechanical/structural calculation based on boom angle, length, and configuration — operator experience is not a variable in the load chart.
During a critical lift, who must review and approve the lift plan?
Answer: A qualified person or licensed PE
Critical lifts require a pre-lift plan reviewed and approved by a qualified person, and in some jurisdictions a licensed professional engineer.
What is the purpose of a crane anti-two-block device?
Answer: It prevents the load block from contacting the boom tip
An anti-two-block (ATB) device stops the hoist when the load block gets too close to the sheave block, preventing catastrophic wire rope failure.