What is the primary purpose of a critical lift plan on a construction site?
Select your answer
A
To document all lifts exceeding 75% of the crane's rated capacity or involving unusual hazards
B
To satisfy insurance requirements for general contractor liability
C
To replace the need for a certified crane operator during complex lifts
D
To eliminate the requirement for a signal person during hoisting operations
Hint