← All CHC Flashcard Decks

Project Planning & Delivery Flashcards

7 cards from real CHC practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Project Planning & Delivery flashcards as text
  1. During preconstruction of a healthcare facility, which document establishes the functional program requirements that drive space planning and room layout decisions?

    Answer: Functional and Space Program (FSP)

    The Functional and Space Program (FSP) defines room counts, sizes, adjacencies, and operational requirements that form the foundation for all healthcare design decisions.

  2. A hospital project is behind schedule during structural steel erection. Which scheduling technique helps the project team identify the most efficient path to recovery?

    Answer: Crashing the critical path with added resources

    Crashing adds resources (labor, equipment) to critical path activities to compress duration, though it increases cost.

  3. What is the purpose of a Guaranteed Maximum Price (GMP) amendment in a healthcare construction contract?

    Answer: It establishes the maximum cost the owner will pay, with savings shared per contract terms

    A GMP sets the ceiling on owner costs while allowing shared savings between owner and contractor as defined in the contract.

  4. Which interim life safety measure (ILSM) is typically required when a fire alarm zone must be taken out of service in an occupied healthcare facility?

    Answer: Posting a fire watch with trained personnel

    NFPA 99 and The Joint Commission require a continuous fire watch when fire detection is impaired in occupied healthcare facilities.

  5. On a healthcare project using Integrated Project Delivery (IPD), at what phase do key trade contractors typically join the project team?

    Answer: During schematic design or early design development

    IPD brings trade partners on board early—often at schematic design—to leverage their expertise in design decisions and improve constructability.

  6. A CHC candidate is reviewing a hospital's equipment plan. Which category of medical equipment is typically furnished by the owner but installed by the contractor (OFOI)?

    Answer: Fixed imaging equipment such as MRI machines

    Fixed imaging equipment like MRI and CT scanners is commonly Owner Furnished/Owner Installed (OFOI) or Owner Furnished/Contractor Installed, requiring coordinated rough-in by the contractor.

  7. During project planning for a healthcare facility, what is the primary purpose of a hazardous materials survey conducted before renovation work begins?

    Answer: To identify asbestos, lead, and other regulated materials requiring abatement

    A hazardous materials survey identifies regulated substances like ACM and lead-based paint that must be abated by licensed contractors before demolition or renovation.