CHC Infection Control & Interim Life Safety Flashcards

7 cards from real CHC practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 CHC Infection Control & Interim Life Safety flashcards as text
  1. During an ICRA, which factor MOST influences the risk classification tier assigned to a construction activity?

    Answer: Proximity to immunocompromised patient care areas

    Proximity to high-risk patient populations such as immunocompromised patients is the primary driver of ICRA risk classification.

  2. An ILSM requires that temporary smoke partitions be constructed within how many hours of a fire barrier being breached for non-emergency work?

    Answer: 8 hours

    NFPA 101 and most facility ILSM policies require temporary smoke barriers to be in place within 8 hours of a fire barrier breach.

  3. Which organism is the PRIMARY airborne fungal pathogen concern in healthcare construction that can cause invasive infections in immunocompromised patients?

    Answer: Aspergillus fumigatus

    Aspergillus fumigatus is the leading cause of invasive pulmonary aspergillosis in immunocompromised patients and is commonly aerosolized during construction.

  4. What is the purpose of a pre-construction walk-through with the Infection Preventionist (IP)?

    Answer: To identify ventilation, water, and patient-proximity risks before work begins

    The pre-construction walk-through allows the IP to identify infection risks specific to the site and establish appropriate mitigation measures before work starts.

  5. Under ILSM, when a required exit becomes temporarily unusable, the facility must ensure alternate exits are:

    Answer: Clearly marked, unobstructed, and communicated to all staff in the affected area

    ILSM requires that alternate exits be clearly identified, free of obstructions, and that staff in the affected areas are informed of the new egress routes.

  6. A contractor notices standing water has accumulated inside a construction enclosure over the weekend. The FIRST action should be to:

    Answer: Notify the healthcare facility's Infection Control and facilities team immediately

    Standing water is a high-risk condition for mold and Legionella growth and must be immediately reported to infection control and facilities for remediation before work resumes.

  7. Which type of construction activity typically requires the HIGHEST level of infection control precautions (Type D/Class IV)?

    Answer: Major demolition adjacent to an occupied bone marrow transplant unit

    Major demolition work in close proximity to highly vulnerable immunocompromised patient populations, such as bone marrow transplant units, requires the most stringent Class IV infection control measures.