← All CHC Flashcard Decks

CHC Cost Management & Contract Administration Flashcards

6 cards from real CHC practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 CHC Cost Management & Contract Administration flashcards as text
  1. A preliminary cost estimate prepared during schematic design is known as:

    Answer: An order-of-magnitude estimate

    An order-of-magnitude estimate is a rough preliminary estimate prepared early in design when project scope is not yet fully defined, typically within +50%/-30% accuracy.

  2. The CSI MasterFormat divides construction costs into:

    Answer: Numbered divisions organized by work type

    CSI MasterFormat organizes construction specifications and cost data into numbered divisions based on work type, providing a universal standard framework for estimating.

  3. What percentage contingency is typically applied to healthcare construction cost estimates at the schematic design phase?

    Answer: 15–25%

    A contingency of 15–25% is typical at schematic design for healthcare projects due to the complexity of the work and undefined scope at early stages.

  4. In healthcare construction budgeting, 'hard costs' refer to:

    Answer: Physical construction labor, materials, and installed equipment

    Hard costs are direct construction costs including labor, materials, and equipment physically incorporated into the completed project.

  5. Soft costs in a healthcare construction project budget include:

    Answer: Design fees, permitting, and owner's project management costs

    Soft costs are indirect project costs such as professional design fees, permits, owner's representative fees, and financing costs.

  6. In a Guaranteed Maximum Price (GMP) contract, cost savings below the GMP typically:

    Answer: Are shared between the owner and contractor per the contract terms

    In a GMP contract, savings below the guaranteed maximum are shared between the owner and contractor according to the agreed-upon split defined in the contract.