Project Management 1 Flashcards
6 cards from real CFM practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 6 Project Management 1 flashcards as text
A facility manager is overseeing a HVAC replacement project that has fallen two weeks behind schedule. Which project management tool best helps identify which tasks must be accelerated to recover the overall timeline?
Answer: Critical path method (CPM) analysis
CPM analysis identifies the sequence of dependent tasks that determine the project's minimum duration. Accelerating tasks on the critical path directly compresses the schedule, whereas speeding up non-critical tasks has no effect on the end date.
During a large facility renovation, the project manager tracks planned value (PV), earned value (EV), and actual cost (AC). If EV is less than AC, what does this indicate?
Answer: The project is over budget for the work completed
When actual cost exceeds earned value, cost variance (CV = EV − AC) is negative, meaning the project is spending more than the budgeted value of work accomplished — a cost overrun condition.
A facility manager is planning a capital project and must present a document that defines scope, schedule, budget, and stakeholder roles before work begins. What is this document called?
Answer: Project charter
A project charter formally authorizes the project, establishes its objectives, defines major milestones, assigns the project manager authority, and identifies key stakeholders — serving as the foundational governance document before detailed planning begins.
Which risk response strategy is being used when a facility manager purchases builder's risk insurance for a major construction project?
Answer: Risk transfer
Risk transfer shifts the financial consequences of a risk to a third party (the insurer) through a contractual mechanism such as insurance. The risk itself is not eliminated, but the organization's financial exposure is reduced by transferring it.
A facility project has a total budget of $500,000 and is 40% complete, but has spent $230,000 to date. What is the cost performance index (CPI)?
Answer: 0.87
CPI = EV ÷ AC. Earned value = 40% × $500,000 = $200,000. CPI = $200,000 ÷ $230,000 ≈ 0.87. A CPI below 1.0 confirms the project is over budget relative to work completed.
A facility manager needs to communicate project status to senior executives who want a high-level overview without detailed scheduling data. Which reporting format is most appropriate?
Answer: Dashboard report with key performance indicators (KPIs)
Executive stakeholders require concise, visual summaries of schedule, budget, and risk status. A dashboard with KPIs delivers this at the right altitude, while detailed Gantt charts, EVM spreadsheets, and network diagrams are more suited to the project team's operational use.