  1. A SWPPP inspection reveals that silt fence has been installed on contours rather than across slopes. What action should the inspector take?

    Answer: Document the deficiency and require corrective action

    Silt fence must intercept sheet flow by running across slopes, not on contours; the inspector must document the deficiency and require corrective installation.

  2. When a SWPPP is revised to add a new sediment basin, the revision must be signed by:

    Answer: A responsible corporate officer or duly authorized representative

    NPDES regulations require that SWPPP amendments be certified and signed by a responsible corporate officer or authorized representative of the permittee.

  3. Which condition would most likely trigger the requirement to update the SWPPP's pollution prevention team contact list?

    Answer: A key responsible party leaving the project

    When a key responsible party leaves the project, the SWPPP contact list must be updated immediately to ensure current personnel are identified for compliance.

  4. Which of the following best describes a 'phased SWPPP'?

    Answer: A SWPPP prepared in stages as site design details become available during construction phases

    A phased SWPPP is developed in stages to match the level of design detail available, with updates as construction phases progress and more site information is known.

  5. A construction site inspector finds that discharge from the site during a storm event is visibly turbid and brown. The first step should be:

    Answer: Document the discharge, assess BMP performance, and determine the source

    The inspector should document the observation, trace the discharge to its source, and evaluate whether BMPs failed or were absent, before determining the appropriate response.

  6. The SWPPP for a linear utility project must address which unique challenge compared to a typical construction site?

    Answer: Multiple points of active disturbance moving along the alignment simultaneously

    Linear projects (pipelines, roads) involve a moving construction front with multiple simultaneous disturbance points that require coordinated, sequential BMP management.

  7. What does the term 'common plan of development' mean in the context of SWPPP and permit coverage requirements?

    Answer: Any contiguous area where multiple construction activities will occur under a single plan

    A 'common plan of development' is a contiguous area planned for construction activities, and all disturbance within it is aggregated to determine permit applicability.