  1. What is the primary purpose of a Stormwater Pollution Prevention Plan (SWPPP)?

    Answer: To document BMPs that minimize pollutant discharges to receiving waters

    A SWPPP identifies and documents the BMPs that will be implemented to minimize the discharge of pollutants in stormwater from a construction site.

  2. Under the NPDES CGP, who is responsible for ensuring the SWPPP is implemented and updated throughout the construction project?

    Answer: The operator(s) with day-to-day site control

    Operators with day-to-day operational control of the site are responsible for SWPPP implementation and must ensure it is current and correctly applied.

  3. Which Clean Water Act Section prohibits the discharge of any pollutant to navigable waters without a permit?

    Answer: Section 301

    Clean Water Act Section 301 prohibits the discharge of pollutants to waters of the US except in compliance with a permit such as an NPDES permit.

  4. A SWPPP inspection reveals a silt fence has failed and sediment has left the site. What is the first required action under the NPDES CGP?

    Answer: Immediately repair the BMP and document the corrective action

    When a BMP failure is observed, the operator must immediately repair it and document the corrective action in the SWPPP inspection records.

  5. What does 'final stabilization' mean in the context of NPDES Construction General Permits?

    Answer: A uniform perennial vegetative cover of 70% has been established, or equivalent stabilization measures are in place

    Final stabilization requires a uniform perennial vegetative cover with 70% density or equivalent non-vegetative measures over all disturbed areas with no potential for discharge.

  6. Which type of water is specifically exempt from NPDES Construction General Permit requirements when discharged from a construction site?

    Answer: Uncontaminated foundation dewatering water meeting permit conditions

    Many NPDES CGPs allow discharge of uncontaminated groundwater or foundation dewatering water provided it meets benchmark turbidity conditions and other requirements.

  7. State NPDES programs that are authorized by the EPA to administer stormwater permits are known as having what status?

    Answer: NPDES primacy