During a post-storm inspection, an inspector finds that a check dam in a swale has been overtopped and partially washed out. What is the correct first step?
Answer: Document the damage with photos and require repair within the timeframe specified by the permit
Post-storm damage must be documented and repaired within permit-specified timeframes, typically within 7 days, to restore BMP function before the next rain event.
Which condition would MOST likely trigger an inspector to recommend a SWPPP amendment?
Answer: A change in site conditions, phasing, or new pollutant sources not covered in the original SWPPP
SWPPP amendments are required when site conditions, construction phasing, or pollutant sources change in ways not addressed by the original plan.
What is the primary purpose of maintaining a chain of evidence and photographic documentation during a CESSWI inspection?
Answer: To provide a legally defensible record of site conditions and compliance status
Thorough photographic and written documentation creates a defensible record that can be used in enforcement actions, legal proceedings, or compliance demonstrations.
An inspector observes concrete washout occurring directly on the ground without a designated washout area. This is a concern primarily because:
Answer: Concrete washout water is highly alkaline and can kill aquatic life if it reaches waterways
Concrete washout water has a very high pH (often above 11) and contains metals that are toxic to aquatic organisms, making containment critical.
When inspecting a stabilized construction entrance, the inspector should verify that:
Answer: The stone apron is adequate depth, width, and length to remove mud from vehicle tires
A stabilized construction entrance must have sufficient stone depth (typically 6 inches), width (12 feet minimum), and length (50 feet minimum) to function as a tire-cleaning BMP.
Who is ultimately responsible for ensuring that the SWPPP is implemented and maintained on a construction site?
Answer: The permittee (owner/operator) of the construction site
The permittee (typically the owner or general contractor) holds the NPDES permit and bears legal responsibility for SWPPP implementation and maintenance.
An inspector finds that vegetation on a previously disturbed slope has less than 70% cover. What does this indicate?
Answer: The stabilization is inadequate and active erosion control BMPs must remain in place