  1. A Black Belt discovers that a process generates 15,000 defects per million opportunities. Without improvement, what is the approximate sigma level of this process?

    Answer: 3.6 sigma

    15,000 DPMO corresponds to approximately 3.6 sigma (short-term), which helps quantify the magnitude of the improvement opportunity during project selection.

  2. Which of the following is the BEST reason to avoid selecting a Six Sigma project that requires a fundamental redesign of a core business system?

    Answer: DMAIC works best when a process already exists and needs optimization

    DMAIC is designed to improve existing processes; projects requiring complete redesign are better suited for DMADV (Design for Six Sigma).

  3. When prioritizing projects using a risk-adjusted NPV, what factor is incorporated that standard NPV does not account for?

    Answer: Probability of project success

    Risk-adjusted NPV multiplies the expected NPV by the probability of success, accounting for project uncertainty during selection.

  4. An organization's voice of the customer (VOC) data shows that delivery speed is the top complaint. Which project selection approach would BEST translate this VOC input into a measurable project goal?

    Answer: Translate VOC into a Critical to Quality (CTQ) characteristic with a specific target

    VOC data must be translated into measurable CTQ characteristics with specific targets before it can drive a meaningful Six Sigma project scope.

  5. A champion is reviewing potential projects and finds one with a high Cost of Poor Quality (COPQ) but low strategic alignment. How should this project be handled?

    Answer: Deprioritize it and look for projects that combine financial impact with strategic alignment

    Best-practice project selection balances both financial impact (COPQ) and strategic alignment; a project strong on only one dimension is typically deprioritized.

  6. Which of the following scenarios represents a correctly scoped Six Sigma project?

    Answer: Reduce the defect rate in the invoice processing step from 8% to less than 1% within six months

    A well-scoped Six Sigma project has a specific process, measurable baseline, defined target, and realistic timeline — like reducing invoice defects from 8% to 1% in six months.

  7. The concept of 'tollgate reviews' during DMAIC serves which project selection/management purpose?

    Answer: Providing go/no-go decision points to ensure projects remain viable and on track

    Tollgate reviews are structured checkpoints at each DMAIC phase where leadership decides whether to continue, redirect, or terminate the project.