← All Certified Six Sigma Black Belt Exam Flashcard Decks

Assessment Flashcards

7 cards from real Certified Six Sigma Black Belt Exam practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Assessment flashcards as text
  1. A team assessing supplier quality uses an attribute agreement analysis. Three appraisers each inspect 30 parts twice. What is the primary metric reported?

    Answer: Kappa statistic (Cohen's Kappa)

    Cohen's Kappa measures agreement between appraisers (and within appraisers vs. reference) beyond chance in attribute measurement system analysis.

  2. During a process assessment, a Black Belt discovers that a key input variable (X) explains 64% of the variation in the output (Y). What is the correlation coefficient (r) between X and Y?

    Answer: 0.80

    R-squared = 0.64 means r = √0.64 = 0.80; the correlation coefficient is the square root of the coefficient of determination.

  3. A Black Belt is assessing whether the variance of a new process is lower than the variance of the existing process. Which hypothesis test is appropriate?

    Answer: F-test (Levene's or Bartlett's test)

    The F-test (or Levene's/Bartlett's test) is used to compare variances between two populations.

  4. In a process assessment, a team identifies 'opportunity' as each solder joint on a circuit board. The board has 200 joints and 8 defects were found across 50 boards. What is the DPMO?

    Answer: 800

    DPMO = (Defects / (Units × Opportunities per unit)) × 1,000,000 = (8 / (50 × 200)) × 1,000,000 = 800 DPMO.

  5. Which assessment method evaluates the risk of a process failure by examining 'what can go wrong' before the process is implemented?

    Answer: Process FMEA (PFMEA)

    Process FMEA (PFMEA) proactively identifies potential failure modes in a process before implementation and assesses their risk via RPN.

  6. A Black Belt assesses process capability using a Ppk of 1.1 and a Cpk of 1.6 for the same process. What does this large gap between Ppk and Cpk suggest?

    Answer: Significant special cause variation is present in the long-term data

    A large gap where Cpk >> Ppk indicates that long-term performance (Ppk) is significantly worse than short-term potential (Cpk), suggesting special cause variation over time.

  7. A team is conducting a process assessment and finds the average cycle time is 45 minutes with a standard deviation of 8 minutes. The upper spec limit is 60 minutes and lower spec limit is 20 minutes. What is Cpk?

    Answer: 0.625

    Cpk = min((USL−mean)/(3σ), (mean−LSL)/(3σ)) = min(15/24, 25/24) = min(0.625, 1.042) = 0.625, indicating the upper spec limit is the binding constraint.