Master Planning of Resources Flashcards
6 cards from real CPIM practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 6 Master Planning of Resources flashcards as text
What is the primary purpose of Sales and Operations Planning (S&OP)?
Answer: To align supply plans with demand plans across the organization
S&OP integrates sales forecasts with production, inventory, and financial plans to create one unified operating plan.
Which planning horizon is most commonly associated with the Master Production Schedule (MPS)?
Answer: Weeks to months
The MPS typically spans weeks to months, covering the planning fence within which firm orders are scheduled.
What does 'demand time fence' mean in master scheduling?
Answer: The period within which changes to the MPS are restricted or require management approval
The demand time fence is the boundary inside which the master scheduler should not change the MPS without senior approval to avoid disrupting firm plans.
Rough-cut capacity planning (RCCP) is performed to verify which plan?
Answer: Master production schedule
RCCP checks the feasibility of the MPS against key resources without the detail of full capacity requirements planning.
In demand management, 'available-to-promise' (ATP) is used to:
Answer: Commit to customer delivery dates based on uncommitted inventory and production
ATP is the uncommitted portion of inventory and planned production that can be promised to new customer orders.
Which technique disaggregates the production plan into a schedule for specific products?
Answer: Master production scheduling
Master production scheduling disaggregates the aggregate production plan into specific product schedules by time period.