  1. What are the three primary inputs to Material Requirements Planning (MRP)?

    Answer: Master production schedule, bill of materials, and inventory records

    MRP requires the MPS to define what and when to produce, the BOM to define component relationships, and inventory records to determine what is on hand or on order.

  2. What does 'net requirements' mean in MRP?

    Answer: Total gross requirements minus on-hand inventory and scheduled receipts

    Net requirements are calculated by subtracting on-hand inventory and scheduled receipts from gross requirements to determine what additional supply is needed.

  3. In MRP, 'lot-for-lot' ordering means:

    Answer: Ordering exactly the net requirement for each period with no extra

    Lot-for-lot (L4L) is an MRP lot-sizing rule that orders exactly the quantity needed each period, minimizing carrying costs but potentially increasing ordering costs.

  4. Capacity Requirements Planning (CRP) operates on which planning inputs?

    Answer: Planned and released work orders from MRP and routing data

    CRP uses MRP-generated planned and released orders along with routing data (operations, run times, setup times) to calculate detailed load on work centers.

  5. What is the purpose of 'pegging' in MRP?

    Answer: Linking component requirements back to the parent demand that caused them

    Pegging traces the source of each component requirement up through the BOM to the specific parent orders or MPS entries that generated them.

  6. An MRP 'action message' to 'reschedule in' means the planner should:

    Answer: Move the due date of an existing order to an earlier date

    A 'reschedule in' message indicates that a scheduled receipt is due after the requirement date and should be expedited or moved earlier.