โ† All CBC Flashcard Decks

CBC Financial Management & Estimating Flashcards

6 cards from real CBC practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 6 CBC Financial Management & Estimating flashcards as text
  1. Which estimating method applies unit costs to each component of work based on material and labor quantities?

    Answer: Unit price estimating

    Unit price estimating calculates costs by multiplying measured quantities of each work item by a predetermined cost per unit.

  2. What does the term 'contingency' refer to in a construction budget?

    Answer: Reserved funds for unforeseen costs

    A contingency is a budgeted reserve set aside to cover unexpected or uncertain costs that may arise during construction.

  3. A contractor's overhead includes which of the following?

    Answer: Office rent and administrative salaries

    Overhead encompasses indirect business costs such as office rent, utilities, and administrative salaries that are not tied to a single project.

  4. What is a Schedule of Values (SOV) used for on a construction project?

    Answer: Breaking the contract sum into line items for progress billing

    A Schedule of Values allocates the total contract amount across work items so that progress payments can be calculated based on percentage of completion.

  5. Which type of bond guarantees that a contractor will complete a project according to the contract terms?

    Answer: Performance bond

    A performance bond protects the owner by ensuring the contractor will fulfill all contractual obligations or the surety will complete the project.

  6. Cash flow management in construction primarily involves:

    Answer: Timing receipts and disbursements to maintain sufficient liquidity

    Effective cash flow management ensures that money coming in from progress payments aligns with money going out for labor, materials, and overhead.