What does a Sprint Burndown Chart track?
Select your answer
A
The cumulative value delivered to customers across all sprints
B
The remaining work (story points or tasks) in a sprint compared to time remaining
C
The number of defects discovered each day during a sprint
D
The team's daily meeting attendance and participation