  1. In Scrum for Service Management, what is the recommended maximum length of a Sprint for service teams?

    Answer: Four weeks

    Sprints in Scrum for Service Management should be four weeks or less to maintain a regular cadence of inspection and adaptation.

  2. Which artifact in Scrum for Service Management replaces the traditional Product Backlog with service-oriented work items?

    Answer: Service Backlog

    The Service Backlog contains prioritized service improvement items, incidents, and requests that the team commits to during Sprint Planning.

  3. What is the primary purpose of the Daily Scrum in a service management context?

    Answer: To synchronize the team's plan for the next 24 hours toward the Sprint Goal

    The Daily Scrum helps the Development Team inspect progress toward the Sprint Goal and adapt the plan for the upcoming day.

  4. How does Scrum for Service Management handle unplanned work such as major incidents during a Sprint?

    Answer: The team allocates a capacity buffer for unplanned work during Sprint Planning

    Service teams typically reserve a percentage of Sprint capacity for unplanned incidents and urgent requests during Sprint Planning.

  5. Which Scrum event is most critical for driving continuous service improvement in Scrum for Service Management?

    Answer: Sprint Retrospective

    The Sprint Retrospective focuses on inspecting how the team worked and identifying improvements, making it the key ceremony for continuous service improvement.

  6. In Scrum for Service Management, who is accountable for maximizing the value delivered by the service team?

    Answer: Product Owner

    The Product Owner is accountable for maximizing the value of the work the team delivers by managing and prioritizing the Service Backlog.