Project Management & Scheduling Flashcards
7 cards from real CEP practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 7 Project Management & Scheduling flashcards as text
In a Precedence Diagramming Method (PDM) network, a Finish-to-Start relationship with a lag of +5 days means the successor activity can start how many days after the predecessor finishes?
Answer: 5 days after
A positive lag in a Finish-to-Start relationship delays the successor's start by the lag duration after the predecessor completes.
Which scheduling technique assigns resources to tasks based on resource availability and attempts to keep resource usage at a constant level?
Answer: Resource leveling
Resource leveling adjusts activity start and finish dates to balance resource demand against supply, often extending the schedule.
A project's Schedule Performance Index (SPI) is 0.85. What does this indicate?
Answer: The project is 15% behind schedule
An SPI below 1.0 means less work was accomplished than planned; an SPI of 0.85 means the project is getting only $0.85 of scheduled work done per $1.00 planned.
Which type of schedule dependency exists when the start of one activity depends on the start of a predecessor activity?
Answer: Start-to-Start
A Start-to-Start relationship requires the predecessor to begin before the successor can begin.
When compressing a project schedule through crashing, which activities should be crashed first?
Answer: Critical path activities with the lowest cost slope
Crashing critical path activities with the lowest cost slope (cost per day saved) provides the maximum schedule compression for minimum additional cost.
In project scheduling, 'free float' is defined as the amount of time an activity can be delayed without affecting:
Answer: The early start of any successor activity
Free float is the delay an activity can sustain without impacting the earliest start of any immediately following activity.
Which scheduling output document typically lists all project activities, their durations, dependencies, and assigned resources in a tabular format?
Answer: Activity list with attributes
The activity list with attributes is a scheduling document that extends the simple activity list with details such as duration, predecessors, successors, and resource requirements.