Mixed Deck — All CEP Topics Flashcards
100 cards from real CEP practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 20 Mixed Deck — All CEP Topics flashcards as text
When planning a Certified Estimating Professional project, what should be established FIRST?
Answer: Clear objectives, scope, and success criteria
Objectives form the foundation for all other planning decisions.
When applying FMEA in the context of cost estimating risk, 'detectability' refers to:
Answer: The likelihood that a failure or error will be caught before it impacts cost
In FMEA, detectability measures how likely it is that existing controls will identify a failure before it causes harm.
A risk register entry shows a risk with probability 0.30 and impact of $80,000. What is the expected monetary value (EMV)?
Answer: $24,000
EMV = Probability × Impact = 0.30 × $80,000 = $24,000.
An estimator reviewing a 'flow-down' clause in a subcontract should understand that it:
Answer: Incorporates prime contract terms into the subcontract, binding the sub to the same obligations
Flow-down clauses pass the relevant obligations of the prime contract down to subcontractors, ensuring consistent terms throughout the contracting chain.
Why is resource leveling important in scheduling?
Answer: To prevent resource conflicts and balance workloads
Resource leveling is a scheduling technique used to adjust the project schedule to optimize the allocation of resources, especially when resources are over-allocated or limited. It helps to smooth out peaks and valleys in resource demand, preventing burnout, improving efficiency, and ensuring that tasks can be completed with available resources.
What distinguishes a Certified Estimating Professional certified professional from non-certified practitioners?
Answer: Validated competency through standardized assessment
Certification provides objective validation through standardized assessment.
A 'factor estimating' method applies percentage factors to which base cost?
Answer: A major purchased equipment or installed equipment cost
Factor estimating (e.g., Lang factor, Hand factor) multiplies purchased or installed equipment cost by empirically derived factors to estimate total facility cost.
Which value engineering job plan phase involves generating creative alternatives without criticism?
Answer: Creative phase
The creative phase uses brainstorming to generate many alternatives without judging their merit.
What does a preliminary estimate provide?
Answer: Early approximate costs
A preliminary estimate, often performed early in the project lifecycle, provides a high-level, approximate cost based on limited information. Its purpose is to give stakeholders an initial idea of the project's financial feasibility and scale, allowing for early decision-making before detailed planning is complete.
A 'spearin doctrine' defense protects a contractor when:
Answer: The owner-furnished specifications are defective, shifting design responsibility to the owner
Under the Spearin Doctrine, an owner impliedly warrants the adequacy of its plans and specifications, making the owner liable when defective specs cause contractor losses.
A contingency reserve addresses which type of risk?
Answer: Known unknowns (identified risks)
Contingency reserve covers identified but uncertain risk events (known unknowns), while management reserve covers unknown unknowns.
What is the MOST important leadership quality for a CEP certified professional?
Answer: Integrity, clear communication, and team development
These qualities build trust and create productive teams.
Which scheduling technique assigns resources to tasks based on resource availability and attempts to keep resource usage at a constant level?
Answer: Resource leveling
Resource leveling adjusts activity start and finish dates to balance resource demand against supply, often extending the schedule.
A 'no damages for delay' clause in a construction contract typically means the contractor:
Answer: Can only recover time, not additional money, for owner-caused delays
A no-damages-for-delay clause limits the contractor's remedy for owner-caused delays to a time extension only, not additional compensation.
When planning a Certified Estimating Professional project, what should be established FIRST?
Answer: Clear objectives, scope, and success criteria
Objectives form the foundation for all other planning decisions.
Which scheduling method links activities using arrows to represent relationships and nodes to represent events, making it an activity-on-arrow network?
Answer: Arrow Diagramming Method (ADM)
The Arrow Diagramming Method (ADM) uses arrows for activities and nodes for events, representing only Finish-to-Start dependencies.
Which correlation coefficient value indicates that two risk variables are perfectly positively correlated in a Monte Carlo model?
Answer: +1.0
A correlation coefficient of +1.0 means the two variables move perfectly in the same direction, maximizing combined variance.
Which stakeholder engagement approach is MOST effective for CEP professionals?
Answer: Identify early, understand interests, maintain regular communication
Early identification with regular communication prevents surprises.
What is the significance of change orders?
Answer: They record approved changes affecting the project
Change orders are formal documents used to modify the original contract, detailing any alterations to the scope of work, schedule, or cost. They are crucial for maintaining clear communication and legal records of all agreed-upon adjustments. This ensures that all parties are aware of and consent to the project's evolution, preventing disputes and ensuring proper compensation.
What is the impact of the 'learning curve' on labor cost estimates for repetitive work?
Answer: Productivity improves as workers repeat the same task, reducing required labor-hours per unit over time
The learning curve effect means workers gain efficiency through task repetition, increasing hourly output and reducing per-unit labor costs as work progresses.