Bid Preparation & Submission Flashcards
7 cards from real CEC practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 7 Bid Preparation & Submission flashcards as text
In sealed bidding, what happens if the bid envelope is opened before the official bid opening time?
Answer: The bid may be disqualified as the integrity of the sealed process is compromised
Premature opening of sealed bids compromises bid security and confidentiality, and the bid may be rejected to protect the integrity of the competitive process.
Which element of a bid submission ensures that a contractor can obtain the required performance and payment bonds if awarded?
Answer: Bonding capacity letter or surety qualification statement
A bonding capacity letter from a surety confirms the contractor's ability to obtain performance and payment bonds in the amount required for the project.
When evaluating subcontractor quotes for inclusion in a bid, an estimator should:
Answer: Verify that the subcontractor's scope matches the specified work before using their number
Scope verification ensures the sub's quote covers all required work; using a quote with gaps can result in costly disputes or change orders.
What is a 'lump sum' bid?
Answer: A single fixed price for all work defined in the contract documents
A lump sum bid means the contractor will complete all specified work for one fixed total price, regardless of actual quantities used.
Which scheduling tool is most commonly used to develop the project schedule included in a bid submission?
Answer: Gantt chart or CPM (Critical Path Method) schedule
CPM schedules and Gantt charts are standard tools for demonstrating project sequencing, duration, and critical path in construction bid submissions.
What does 'front-loading' a schedule of values mean in the context of bidding?
Answer: Assigning higher values to early work items to improve early cash flow
Front-loading assigns higher values to early-completing line items to generate positive cash flow early in the project, though owners and lenders monitor for excessive front-loading.
A 'notice of award' differs from a 'notice to proceed' in that:
Answer: Notice of award informs the contractor they are selected; notice to proceed authorizes construction to begin
The notice of award selects the contractor and initiates contract execution, while the notice to proceed is the formal authorization to begin physical construction work.