In a Design-Bid-Build delivery method, what is the sequence of project phases?
Select your answer
A
Design and construction overlap; contractor joins early
B
Design is completed, then bids are solicited, then construction begins
C
Owner selects contractor first, then design begins
D
Design and construction proceed simultaneously under one contract