(CCT) Certified Cost Technician Practice Test
CCT Earned Value Management
What does Earned Value (EV) represent in Earned Value Management?
Select your answer
A
The actual cost of work performed to date
B
The budgeted cost of work scheduled to be done
C
The budgeted value of work actually completed
D
The forecasted cost at project completion