Schedule Coordination & OPR Flashcards

7 cards from real CCP practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Schedule Coordination & OPR flashcards as text
  1. An OPR document lists energy performance targets. At what project phase should these targets first be verified against actual system performance?

    Answer: During functional performance testing

    Functional performance testing is the phase where actual system operation is measured and compared against OPR energy targets.

  2. Which item should be included in the OPR to guide the commissioning schedule for a data center project?

    Answer: Uptime requirements and allowable maintenance windows

    Uptime requirements and allowable maintenance windows directly dictate when commissioning testing can occur without disrupting operations.

  3. What does schedule float represent in the context of commissioning?

    Answer: The amount of time a commissioning task can be delayed without affecting project completion

    Float is the allowable delay in a non-critical commissioning task before it impacts the overall project completion date.

  4. The OPR specifies that the owner's facilities staff must be trained before occupancy. Where should this requirement appear in the commissioning schedule?

    Answer: As a milestone prior to occupancy, after systems are verified operational

    Training is most effective after systems are verified functional but before occupancy so staff can operate the building from day one.

  5. Which document bridges the OPR and the commissioning schedule by translating owner requirements into specific design criteria?

    Answer: Basis of Design (BOD)

    The Basis of Design translates OPR goals into specific design approaches and criteria that the commissioning schedule then verifies.

  6. A commissioning schedule shows seasonal testing of economizer operation planned for winter. The OPR requires verification of summer cooling capacity. What action is required?

    Answer: Add a summer functional performance test to verify cooling capacity per OPR

    The OPR requirement for summer cooling verification must be addressed by scheduling functional performance testing during or simulating summer conditions.

  7. In multi-phase construction, how should the commissioning schedule address systems serving both completed and ongoing construction zones?

    Answer: Commission systems in phases aligned with each zone's occupancy readiness

    Phased commissioning aligns with phased occupancy, ensuring each zone's systems meet OPR requirements before that area is occupied.