← All CCP Flashcard Decks

Regulatory Standards Flashcards

7 cards from real CCP practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Regulatory Standards flashcards as text
  1. Which ASHRAE guideline specifically addresses the commissioning process for existing buildings and systems?

    Answer: ASHRAE Guideline 0.2-2015

    ASHRAE Guideline 0.2-2015 covers the commissioning process specifically for existing buildings and systems (retrocommissioning).

  2. Under LEED v4, which prerequisite requires commissioning of fundamental building systems?

    Answer: EA Prerequisite: Fundamental Commissioning and Verification

    The EA (Energy and Atmosphere) Prerequisite: Fundamental Commissioning and Verification requires that building energy systems be commissioned per ASHRAE Guideline 0.

  3. What is the primary purpose of ASHRAE Standard 202-2018 in commissioning practice?

    Answer: To define the commissioning process for building systems

    ASHRAE Standard 202-2018, 'Commissioning Process for Buildings and Systems,' formally defines the commissioning process, making it an ANSI-approved standard rather than just a guideline.

  4. Which federal regulation requires retrocommissioning of federal agency buildings over 50,000 square feet?

    Answer: Energy Independence and Security Act (EISA) 2007

    EISA 2007 Section 432 requires federal agencies to commission or retrocommission covered facilities exceeding 50,000 gross square feet.

  5. In California, which Title 24 section specifically addresses building commissioning requirements for nonresidential buildings?

    Answer: Title 24 Part 6 (Energy Code), Section 120.8

    California Title 24 Part 6, Section 120.8 contains the commissioning requirements for nonresidential buildings, including what systems must be commissioned and documentation standards.

  6. Which organization publishes the National Electrical Code (NEC) that commissioning professionals must reference for electrical system verification?

    Answer: NFPA

    The National Fire Protection Association (NFPA) publishes NFPA 70, the National Electrical Code, which governs electrical installations verified during commissioning.

  7. When a commissioning provider discovers a code violation during functional testing, what is the proper course of action per standard commissioning protocols?

    Answer: Document the issue in the commissioning report and notify the owner and design team

    The commissioning provider must document deficiencies—including code violations—in the commissioning report and formally notify the owner and design team for resolution.