Cx Process & ASHRAE Guideline 0 Flashcards

7 cards from real CCP practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Cx Process & ASHRAE Guideline 0 flashcards as text
  1. According to ASHRAE Guideline 0, who is responsible for developing the Owner's Project Requirements (OPR)?

    Answer: The owner with assistance from the CxA

    ASHRAE Guideline 0 assigns responsibility for developing the OPR to the owner, typically with facilitation and assistance from the commissioning authority.

  2. During which commissioning phase is the Systems Manual first compiled?

    Answer: Construction phase

    The Systems Manual begins to be compiled during the construction phase as equipment is installed and tested, then finalized before occupancy.

  3. What is the primary purpose of the Basis of Design (BOD) document in the Cx process?

    Answer: To document the design intent and assumptions that fulfill the OPR

    The BOD documents the design engineer's reasoning, assumptions, and technical approach used to satisfy the Owner's Project Requirements.

  4. Which statement best describes the role of 'deferred commissioning' under ASHRAE Guideline 0?

    Answer: Formal Cx tasks that cannot be completed before occupancy and are scheduled for a defined future date

    Deferred commissioning refers to Cx activities that cannot be completed before occupancy but are formally documented and scheduled to occur at a specified future date.

  5. In the ASHRAE Guideline 0 Cx process, what document formally records deficiencies found during testing?

    Answer: Issues Log

    The Issues Log (also called a Deficiency Log) tracks all problems identified during commissioning, including their status and resolution.

  6. ASHRAE Guideline 0 identifies five commissioning phases. Which phase immediately precedes the Construction phase?

    Answer: Design

    The five phases in order are Pre-design, Design, Construction, Acceptance, and Occupancy & Operations; Design immediately precedes Construction.

  7. What is a key CxA deliverable at the end of the Acceptance Phase according to ASHRAE Guideline 0?

    Answer: Final Commissioning Report

    The Final Commissioning Report, summarizing all Cx activities, test results, and resolved issues, is the primary CxA deliverable at acceptance phase completion.