Cx Plan & Issues Log Flashcards

7 cards from real CCP practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Cx Plan & Issues Log flashcards as text
  1. Which section of the Cx Plan defines the roles and responsibilities of the commissioning team members?

    Answer: Commissioning Team Organization

    The Commissioning Team Organization section of the Cx Plan identifies each team member's role, authority, and responsibilities throughout the project.

  2. An Issues Log entry is flagged as 'critical' — what distinguishes it from a 'minor' issue?

    Answer: It affects life safety, building occupancy, or fundamental system operation

    Critical issues are those that impact life safety, occupancy, or the fundamental ability of a system to perform its intended function.

  3. When should the Cx Plan first be developed on a new construction project?

    Answer: During the design development phase or earlier

    The Cx Plan should be initiated during design development or even pre-design to maximize influence over the design and construction process.

  4. Which document is most commonly used as the master reference for identifying system performance expectations in the Cx Plan?

    Answer: Owner's Project Requirements (OPR)

    The Owner's Project Requirements (OPR) defines the performance expectations and goals that the Cx Plan and all commissioning activities are designed to verify.

  5. In an Issues Log, what does the field 'responsible party' capture?

    Answer: The individual or firm accountable for resolving the issue

    The 'responsible party' field identifies who is assigned to correct the deficiency, ensuring clear accountability for resolution.

  6. A Cx Plan for a large hospital project should include provisions for which of the following that a small office project might omit?

    Answer: Seasonal and integrated systems testing

    Complex facilities like hospitals require seasonal and integrated systems testing to verify performance under varying load conditions not present during a single construction-phase test.

  7. Which Issues Log status code indicates that a deficiency has been corrected and verified by the CxA?

    Answer: Closed

    A 'Closed' status means the responsible party has corrected the issue and the CxA has independently verified the correction is acceptable.