When auditing a construction project's contingency reserve, an auditor should verify that the reserve is:
Answer: Separately identified and subject to owner approval for use
Contingency reserves should be explicitly tracked and require owner authorization before drawdown to prevent unauthorized spending.
Which internal control helps prevent a project manager from approving their own invoices on a construction project?
Answer: Dual-signature requirement for payments
Requiring two authorized signatures on payment approvals ensures no single individual can unilaterally approve their own expenditures.
An auditor finds that a construction project's work breakdown structure (WBS) does not align with its cost codes. This discrepancy most likely impairs:
Answer: Accurate cost tracking and performance measurement
Misalignment between the WBS and cost codes makes it impossible to accurately track costs by work package and measure performance.
In construction project auditing, a 'look-ahead schedule' is primarily reviewed to assess:
Answer: Near-term work planning and resource availability
A look-ahead schedule (typically 3–6 weeks) documents near-term work plans and reveals whether resources and materials are being properly coordinated.
Which variance threshold trigger should a construction auditor recommend as a best practice for mandatory management reporting?
Answer: Variances exceeding 5–10% of budget or a defined dollar threshold
A percentage or dollar threshold (commonly 5–10%) ensures significant variances receive management attention without creating noise from minor fluctuations.
A construction project auditor detects that baseline schedules have been revised multiple times without documented owner approval. This is an indicator of:
Answer: Unauthorized schedule manipulation
Repeated baseline revisions without owner approval may hide schedule slippage and distort performance metrics.