← All CAPM Flashcard Decks

Project Scheduling & Critical Path Flashcards

7 cards from real CAPM practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Project Scheduling & Critical Path flashcards as text
  1. A project manager uses Monte Carlo simulation on the project schedule. What is the primary purpose of this technique?

    Answer: To assess schedule risk and quantify the probability of meeting target dates

    Monte Carlo simulation runs many iterations with varied activity durations to produce a probability distribution for project completion dates.

  2. In the Schedule Network Analysis, what is the difference between total float and free float?

    Answer: Total float measures delay impact on the project; free float measures delay impact on immediate successors

    Total float is the time an activity can be delayed without delaying the project end, while free float is the delay allowed without pushing the next activity's early start.

  3. Which of the following BEST describes a Start-to-Start (SS) dependency with a lag of 2 days?

    Answer: The successor cannot start until 2 days after the predecessor starts

    An SS+2 relationship means the successor activity can start only after the predecessor has been underway for 2 days.

  4. A project's Earned Value is $80,000 and Planned Value is $100,000. What is the Schedule Variance (SV)?

    Answer: -$20,000

    Schedule Variance = EV − PV = $80,000 − $100,000 = −$20,000, indicating the project is behind schedule.

  5. When is it appropriate to use the Schedule Compression technique of crashing?

    Answer: When the project has unlimited budget and needs to finish earlier

    Crashing is appropriate when time must be reduced and additional budget is available, as it adds resources to shorten critical path activity durations.

  6. Which artifact is used to visualize project activities against a calendar timeline with bars representing duration?

    Answer: Gantt chart

    A Gantt chart displays project activities as horizontal bars on a calendar timeline, making it easy to see task durations and scheduling.

  7. A project manager identifies that an activity on the critical path is taking longer than planned. Which is the FIRST action to take?

    Answer: Analyze the impact and update the schedule forecast

    The first step is to analyze the delay's impact on the schedule and update forecasts before deciding on corrective actions.