  1. Which type of organizational structure gives the project manager the MOST authority?

    Answer: Projectized

    In a projectized organization, project managers have full authority over resources and project decisions.

  2. A project has a Budget at Completion (BAC) of $200,000, Earned Value (EV) of $80,000, and Actual Cost (AC) of $100,000. What is the Estimate to Complete (ETC) using the typical ETC formula?

    Answer: $150,000

    ETC = (BAC - EV) / CPI = ($200,000 - $80,000) / 0.80 = $150,000, where CPI = EV/AC = 0.80.

  3. What is the primary purpose of the project communications management plan?

    Answer: Define who receives what information, when, and how

    The communications management plan defines the information needs of stakeholders and how communications will be handled.

  4. Which estimating technique uses historical data from previous similar projects as a basis for estimating the current project?

    Answer: Analogous estimating

    Analogous estimating uses historical data from similar past projects and is typically less accurate but faster and cheaper.

  5. During project closure, which activity is MOST important for organizational learning?

    Answer: Conducting lessons learned sessions

    Lessons learned sessions capture knowledge from the project that can improve performance on future projects.

  6. A project manager wants to show the relationship between two variables to determine if they are correlated. Which quality tool should be used?

    Answer: Scatter diagram

    A scatter diagram plots two variables to show if a relationship or correlation exists between them.

  7. The critical path in a project schedule represents:

    Answer: The longest path through the network that determines project duration

    The critical path is the longest duration path through the project network, which sets the earliest possible completion date.