Control Account Manager (CAM) Certification — Questions and Answers
Question 1: What is the primary purpose of a Resource Breakdown Structure (RBS) in a control account?
- To organize and categorize the types of resources needed to complete project work (Correct answer)
- To list all project deliverables by category
- To document resource costs in the cost baseline
- To define the hierarchy of project stakeholders
Correct answer: To organize and categorize the types of resources needed to complete project work
The RBS categorizes resources (labor, materials, equipment) hierarchically to facilitate resource planning, allocation, and tracking within control accounts.
Question 2: Which of the following is a key element of maintaining data integrity in earned value management?
- Adjusting percent complete to match spent costs
- Setting all work packages to level-of-effort measurement
- Allowing retroactive changes to closed accounting periods
- Ensuring performance is claimed only per pre-defined earning rules (Correct answer)
Correct answer: Ensuring performance is claimed only per pre-defined earning rules
Claiming performance strictly by established earning rules prevents subjective or inflated progress claims.
Question 3: A subcontractor performs 30% of a control account's discrete work. How should the CAM incorporate the subcontractor's performance?
- Report subcontract cost as level of effort regardless of work type
- Integrate subcontractor earned value data into the control account consistent with the EVMS (Correct answer)
- Claim 100% earned value when the subcontract is signed
- Exclude subcontract effort from earned value entirely
Correct answer: Integrate subcontractor earned value data into the control account consistent with the EVMS
Subcontracted discrete effort must be measured and integrated into the prime's control account performance data.
Question 4: Which element of a control account plan time-phases the budget over the period of performance?
- The management reserve log
- The subcontract terms and conditions
- The actual cost ledger
- The BCWS spread by accounting period (Correct answer)
Correct answer: The BCWS spread by accounting period
The time-phased BCWS establishes when budget is planned to be earned, forming the account's schedule baseline for measurement.
Question 5: A control account has a BAC of $500,000, an EV of $200,000, and an AC of $250,000. What is the Cost Performance Index (CPI)?
- 1.25
- 0.40
- 0.50
- 0.80 (Correct answer)
Correct answer: 0.80
CPI = EV / AC = $200,000 / $250,000 = 0.80, meaning the account earns $0.80 of value per dollar spent.
Question 6: What is the Variance at Completion (VAC) if BAC is $800,000 and EAC is $920,000?
- −$80,000
- +$920,000
- +$120,000
- −$120,000 (Correct answer)
Correct answer: −$120,000
VAC = BAC − EAC = $800,000 − $920,000 = −$120,000, a projected overrun.
Question 7: Which schedule metric indicates whether a project is ahead of or behind its planned schedule?
- Cost Variance (CV)
- Cost Performance Index (CPI)
- Budget at Completion (BAC)
- Schedule Variance (SV) (Correct answer)
Correct answer: Schedule Variance (SV)
Schedule Variance (SV = EV – PV) measures whether the project is ahead of or behind the planned schedule.
Question 8: Which earned value technique setting in an EVM tool is most appropriate for a short, discrete work package spanning two accounting periods?
- 50/50 milestone technique (Correct answer)
- No technique needed
- Level of effort
- Apportioned effort against another account
Correct answer: 50/50 milestone technique
Short discrete work packages spanning two periods commonly use the 50/50 technique, claiming half at start and half at completion.
Question 9: What is the primary goal of cost control in project management?
- To keep project costs within budget (Correct answer)
- To increase project expenditures
- To focus only on revenue generation
- To eliminate the need for budgeting
Correct answer: To keep project costs within budget
The primary goal of cost control in project management is to monitor project expenditures, manage changes to the cost baseline, and ensure that project costs remain within the approved budget. This involves identifying variances from the plan and taking corrective actions to bring costs back into alignment. Effective cost control is crucial for project financial health and success.
Question 10: Which entity audits contractor accounting systems and incurred costs supporting EVMS data on government contracts?
- Federal Trade Commission
- Small Business Administration
- Defense Contract Audit Agency (DCAA) (Correct answer)
- Securities and Exchange Commission
Correct answer: Defense Contract Audit Agency (DCAA)
DCAA audits contractor accounting systems and costs, complementing DCMA's EVMS compliance oversight.
Question 11: A CAM is presenting a recovery plan after a rebaseline was approved. Which statement to stakeholders correctly characterizes the change?
- The rebaseline erased the prior overrun, so the program is now on budget
- The rebaseline means prior performance data is no longer relevant to forecasts
- Historical variances were retained where required, and the new baseline reflects a realistic plan for remaining work going forward (Correct answer)
- The customer no longer receives variance reports after a rebaseline
Correct answer: Historical variances were retained where required, and the new baseline reflects a realistic plan for remaining work going forward
A proper rebaseline creates a realistic go-forward plan while preserving the historical performance record.
Question 12: Who typically controls the release of management reserve to a control account?
- The payroll department
- The program manager, through a documented budget change process (Correct answer)
- The customer's contracting officer
- The CAM, at their own discretion
Correct answer: The program manager, through a documented budget change process
Management reserve is owned by the program manager and released only through formal, logged budget change control.
Question 13: Actual costs in a control account should be recorded in a manner consistent with which other element?
- The customer's fiscal year appropriation categories
- The company's marketing forecast
- The way the corresponding budget was planned and earned value is claimed (Correct answer)
- The management reserve drawdown schedule
Correct answer: The way the corresponding budget was planned and earned value is claimed
Budget, earned value, and actual cost must be recorded consistently so variances are meaningful.
Question 14: A control account has three work packages using 0/100, 50/50, and percent complete techniques. What determines EV at the control account level?
- The average of the three techniques applied to BAC
- The technique used by the largest work package applied to all
- The sum of earned value from each work package (Correct answer)
- The planned value of the earliest work package
Correct answer: The sum of earned value from each work package
Control account EV is simply the sum of the EV claimed by each of its work packages.
Question 15: What does 'resource smoothing' differ from 'resource leveling' in scheduling?
- Resource smoothing extends the project end date; resource leveling does not
- Resource smoothing adjusts resources within float limits without changing the critical path; resource leveling may extend the schedule (Correct answer)
- Resource smoothing only applies to labor; resource leveling applies to all resource types
- Resource smoothing is used for baseline changes; resource leveling is used for variance analysis
Correct answer: Resource smoothing adjusts resources within float limits without changing the critical path; resource leveling may extend the schedule
Resource smoothing optimizes resource usage within available float, preserving the project end date, while resource leveling may extend the schedule to eliminate over-allocations.
Question 16: In Control Account Manager Certification practice, what should a professional do when facing a conflict of interest?
- Hide the conflict from others
- Ignore it and proceed
- Let someone else decide
- Disclose the conflict and recuse if necessary (Correct answer)
Correct answer: Disclose the conflict and recuse if necessary
Disclosing conflicts of interest maintains transparency and trust, allowing appropriate action to be taken to prevent bias.
Question 17: A schedule variance is traced to a delayed material delivery. Which corrective action most directly addresses the root cause?
- Submit a contract change request immediately
- Increase the budget for the affected work package
- Expedite the material delivery or re-sequence work to utilize available resources productively (Correct answer)
- Crash the schedule by adding labor to all critical path activities
Correct answer: Expedite the material delivery or re-sequence work to utilize available resources productively
Re-sequencing work or expediting the delivery directly attacks the root cause (material unavailability) while keeping the workforce productive during the delay.
Question 18: During an EVMS review, the customer asks how subcontractor performance data quality is assured before integration into the prime's reports. Which answer reflects best practice?
- The prime flows down EVM requirements, reviews subcontractor data for anomalies, and integrates it through documented procedures (Correct answer)
- Subcontractor performance is excluded from the prime's reports
- Subcontractor data is entered exactly as received without review
- The prime replaces subcontractor data with its own estimates
Correct answer: The prime flows down EVM requirements, reviews subcontractor data for anomalies, and integrates it through documented procedures
Primes must flow down requirements and apply documented review and integration procedures to subcontractor data.
Question 19: A CAM maintains a notebook (or electronic equivalent) for their control account. What is its primary purpose?
- To track personal performance goals
- To store customer contact information
- To replace the program's official cost accounting system
- To provide an organized, auditable record of all control account documentation (Correct answer)
Correct answer: To provide an organized, auditable record of all control account documentation
The CAM notebook consolidates work authorizations, budgets, schedules, and variance analyses into one auditable reference.
Question 20: In EVMS, what is the role of the Integrated Master Schedule (IMS)?
- To provide a networked schedule linking all project work to milestones and deliverables (Correct answer)
- To track subcontractor payments
- To define the organizational breakdown structure
- To document all project costs
Correct answer: To provide a networked schedule linking all project work to milestones and deliverables
The IMS is a networked, time-phased schedule that integrates all project tasks, milestones, and deliverables to support EVMS reporting.
Question 21: The Truthful Cost or Pricing Data statute (formerly the Truth in Negotiations Act) primarily requires contractors to:
- Hire government auditors as consultants
- Use only fixed-price contract types
- Disclose all employee salaries publicly
- Submit and certify current, accurate, and complete cost or pricing data for covered contract actions (Correct answer)
Correct answer: Submit and certify current, accurate, and complete cost or pricing data for covered contract actions
TINA requires certified cost or pricing data that is current, accurate, and complete for negotiated actions above the threshold.
Question 22: What is 'over-allocation' in resource management?
- Allocating resources to non-critical path activities first
- Distributing overhead costs across too many control accounts
- Assigning more budget than the WBS element requires
- Assigning a resource to more work than it can complete within the available time (Correct answer)
Correct answer: Assigning a resource to more work than it can complete within the available time
Over-allocation occurs when a resource is assigned to more work than its availability allows in a given timeframe, creating a resource conflict.
Question 23: Which element is NOT part of the Performance Measurement Baseline?
- Undistributed budget
- Summary level planning packages
- Distributed budget in control accounts
- Management reserve (Correct answer)
Correct answer: Management reserve
Management reserve is held outside the PMB for unknown risks, while distributed budget, undistributed budget, and summary level planning packages are within it.
Question 24: Which budgeting method allocates funds based on prior period spending?
- Zero-based budgeting
- Activity-based budgeting
- Historical budgeting (Correct answer)
- Rolling budgeting
Correct answer: Historical budgeting
Historical budgeting is a method where the current budget is prepared by using past period's budget or actual performance as a baseline. Adjustments are then made for anticipated changes, such as inflation or new activities. While simple, it can perpetuate inefficiencies if not critically reviewed.
Question 25: Which of the following best describes 'schedule compression'?
- Reducing project scope to meet the schedule
- Techniques used to shorten project duration without reducing scope (Correct answer)
- Removing activities from the critical path
- Extending the schedule to accommodate resource constraints
Correct answer: Techniques used to shorten project duration without reducing scope
Schedule compression techniques such as crashing and fast-tracking shorten project duration while maintaining the original project scope.
Question 26: Which type of cost is directly traceable to a single control account and should be assigned directly rather than allocated?
- Direct costs (Correct answer)
- G&A costs
- Overhead costs
- Indirect costs
Correct answer: Direct costs
Direct costs are those specifically identifiable to a single control account or work package and must be directly charged rather than allocated through overhead rates.
Question 27: A CAM decides to subcontract a high-risk fabrication task to a vendor with proven expertise, shifting the consequence to the vendor. Which risk response strategy is this?
- Mitigate
- Avoid
- Transfer (Correct answer)
- Accept
Correct answer: Transfer
Shifting risk ownership and consequence to a third party, such as through subcontracting or insurance, is risk transfer.
Question 28: A CAM's spouse owns stock in a subcontractor the CAM will evaluate for a make-or-buy decision. The correct action is:
- Vote against the subcontractor to appear unbiased
- Proceed since the stock belongs to the spouse, not the CAM
- Sell the stock secretly after the decision
- Disclose the financial interest and recuse from the decision if directed (Correct answer)
Correct answer: Disclose the financial interest and recuse from the decision if directed
Household financial interests create conflicts that must be disclosed before participating in the decision.
Question 29: A CAM is asked by a program manager to set earned value equal to actual costs to eliminate a cost variance. What should the CAM do?
- Comply, since the program manager has authority over the baseline
- Transfer the variance to management reserve
- Refuse, because manipulating earned value violates EVMS integrity requirements (Correct answer)
- Comply, but only for one reporting period
Correct answer: Refuse, because manipulating earned value violates EVMS integrity requirements
Setting earned value to match actuals falsifies performance data and violates EVMS guidelines and federal reporting integrity rules.
Question 30: A CAM identifies a risk that, if realized, will require unplanned in-scope work. Where should the budget for this potential work come from?
- Deleting scope from future work packages
- The customer's fee pool
- Management reserve, released through formal change control (Correct answer)
- Another CAM's underrunning work package
Correct answer: Management reserve, released through formal change control
Management reserve exists for unplanned in-scope work and is released to control accounts through the formal change process.
Question 31: What is the significance of the 'responsibility assignment matrix (RAM)' in a control account?
- It maps WBS elements to OBS units to formally assign accountability for each control account (Correct answer)
- It documents the project's risk register by responsible owner
- It defines the sequence of resource acquisition activities
- It tracks actual resource expenditures against the budget
Correct answer: It maps WBS elements to OBS units to formally assign accountability for each control account
The RAM maps WBS elements against OBS units at the control account level, clearly establishing who is accountable for each piece of work and budget.
Question 32: Which cost estimation technique relies on expert judgment and past project data?
- Analogous estimating (Correct answer)
- Parametric estimating
- Monte Carlo simulation
- Bottom-up estimating
Correct answer: Analogous estimating
Analogous estimating is a top-down cost estimation technique that uses the actual cost or duration of a previous, similar project as the basis for estimating the current project. It relies heavily on expert judgment and historical data, making it a quick but less precise method, often used in the early stages of a project when detailed information is scarce.
Question 33: Which risk response strategy involves transferring risk responsibility to a third party?
- Risk transfer (Correct answer)
- Risk escalation
- Risk avoidance
- Risk mitigation
Correct answer: Risk transfer
Risk transfer is a strategy where the responsibility for managing a risk, and often its potential financial impact, is shifted to a third party. This is commonly achieved through mechanisms like purchasing insurance, implementing warranties, or outsourcing specific project components to specialists. By transferring the risk, the original party reduces its direct exposure to potential losses.
Question 34: What is the To-Complete Performance Index (TCPI) based on BAC if BAC = $1,000,000, EV = $400,000, and AC = $500,000?
- 0.83
- 0.80
- 1.20 (Correct answer)
- 1.00
Correct answer: 1.20
TCPI = (BAC − EV) / (BAC − AC) = $600,000 / $500,000 = 1.20, the efficiency needed to finish on budget.
Question 35: During an Integrated Baseline Review (IBR), what is a primary risk-related objective?
- Setting the contract ceiling price
- Assessing whether the baseline realistically captures technical, schedule, and cost risks (Correct answer)
- Approving the contractor's award fee
- Eliminating all risks before work begins
Correct answer: Assessing whether the baseline realistically captures technical, schedule, and cost risks
The IBR evaluates baseline realism and mutual understanding of the risks inherent in the plan.
Question 36: Which scenario would most likely trigger a government-initiated EVMS review for cause?
- The contractor hiring new CAMs
- Routine on-time IPMDAR deliveries
- Recurring data anomalies such as frequent retroactive changes and unexplained variances (Correct answer)
- A single month of favorable cost variance
Correct answer: Recurring data anomalies such as frequent retroactive changes and unexplained variances
Patterns like repeated retroactive changes or unexplained data anomalies signal systemic problems and can trigger a review for cause.
Question 37: A control account's cumulative cost variance exceeds the reporting threshold. What must the CAM prepare?
- A retroactive change to the baseline to eliminate the variance
- A request to raise the threshold so the variance no longer reports
- A variance analysis report explaining cause, impact, and corrective action (Correct answer)
- A transfer of the variance to management reserve
Correct answer: A variance analysis report explaining cause, impact, and corrective action
Threshold breaches require a variance analysis documenting root cause, impact, and the corrective action plan.
Question 38: Which EVMS criterion requires that the CAM's control account budget be traceable to the contract budget base?
- Criteria 22 – Indirect costs
- Criteria 8 – Baseline (Correct answer)
- Criteria 1 – Organization
- Criteria 32 – Revisions and data maintenance
Correct answer: Criteria 8 – Baseline
EVMS Criterion 8 (Baseline) requires that all budgets in control accounts are traceable to the Contract Budget Base and are properly time-phased in the PMB.
Question 39: Why is retroactively changing budgets for completed work generally prohibited in an EVMS?
- It distorts historical performance data and masks true variances (Correct answer)
- It converts management reserve into fee
- It automatically increases the contract value
- It requires too much administrative effort
Correct answer: It distorts historical performance data and masks true variances
Retroactive changes erase the performance record and hide overruns, undermining baseline integrity.
Question 40: A CAM's control account shows a favorable cost variance, but the risk register lists an unmitigated technical risk in a future work package. How should the CAM report status?
- Delay reporting until the risk is retired
- Report only the favorable variance since risks are the risk manager's job
- Report the favorable variance and explicitly note the open risk to future performance in the variance analysis (Correct answer)
- Offset the favorable variance against the risk exposure and report zero variance
Correct answer: Report the favorable variance and explicitly note the open risk to future performance in the variance analysis
Accurate status requires reporting current performance alongside known risks that threaten future performance.
Question 41: What is 'authorized unpriced work (AUW)' in resource and budget management?
- Work that has been authorized by management but for which the final price has not yet been negotiated or agreed upon (Correct answer)
- Overhead work authorized but not assigned to any control account
- Subcontract work approved but not yet awarded to a vendor
- Work performed outside the contract scope without approval
Correct answer: Work that has been authorized by management but for which the final price has not yet been negotiated or agreed upon
AUW is work that has been formally authorized to proceed but where the negotiated price has not yet been finalized, requiring interim budget to be placed in the PMB.
Question 42: What is the purpose of a 'schedule risk analysis' in CAM practice?
- To document lessons learned from past schedule overruns
- To quantify schedule uncertainty and determine the probability of meeting milestone dates (Correct answer)
- To assign float to all critical path activities
- To identify activities that can be eliminated from the schedule
Correct answer: To quantify schedule uncertainty and determine the probability of meeting milestone dates
Schedule risk analysis, often performed using Monte Carlo simulation, quantifies the probability of completing the project within a given timeframe.
Question 43: Which FAR-level policy document establishes earned value management requirements for major acquisitions across all federal civilian agencies?
- OMB Circular A-11 (Capital Programming Guide) (Correct answer)
- FAR Part 45 government property
- OMB Circular A-133
- FAR Part 12 commercial items
Correct answer: OMB Circular A-11 (Capital Programming Guide)
OMB Circular A-11 and its Capital Programming Guide require EVMS on major federal capital acquisitions government-wide.
Question 44: A CAM discovers that budget was transferred from a future work package to cover a current overrun without any scope transfer. What compliance problem does this represent?
- Acceptable management reserve usage
- A normal replanning action requiring no documentation
- Retroactive or improper budget shifting that masks true performance (Correct answer)
- An authorized undistributed budget allocation
Correct answer: Retroactive or improper budget shifting that masks true performance
Moving budget without corresponding scope hides variances and violates EVMS guidelines on maintaining baseline integrity.
Question 45: A CAM must document a change to the performance measurement baseline. Which record captures the change and its approval?
- A revised invoice to the customer
- An informal email to the team
- A handwritten note in the schedule margin
- A Baseline Change Request with an updated change control log (Correct answer)
Correct answer: A Baseline Change Request with an updated change control log
Baseline changes must be documented through formal change requests and logged to maintain traceability of the performance measurement baseline.
Question 46: What is a Corrective Action Plan (CAP) primarily designed to accomplish?
- Identify specific actions to bring a control account back within acceptable performance thresholds (Correct answer)
- Document the historical record of past variances
- Request additional budget from management reserves
- Justify the validity of original cost estimates
Correct answer: Identify specific actions to bring a control account back within acceptable performance thresholds
A CAP identifies specific actions, responsible parties, and timelines to address root causes and recover performance to acceptable levels going forward.
Question 47: A CAM's variance analysis report must include which three core elements to be considered complete?
- Staffing plan, org chart, and RAM
- Budget, funding, and profit analysis
- Root cause, impact, and corrective action plan (Correct answer)
- Contract value, fee, and invoice status
Correct answer: Root cause, impact, and corrective action plan
Complete variance analysis explains why the variance occurred, what it affects, and how it will be corrected or managed.
Question 48: Which statement best describes a CAM's ethical responsibility when delegating work authorization?
- Delegation is prohibited under EVMS standards
- The CAM retains accountability for the control account even when tasks are delegated (Correct answer)
- Delegation transfers all accountability to the delegate
- Accountability shifts to the program manager upon delegation
Correct answer: The CAM retains accountability for the control account even when tasks are delegated
Delegation assigns tasks but the CAM remains accountable for control account performance and integrity.
Question 49: A control account's budget may be changed retroactively under EVMS rules only when:
- The customer verbally approves the change
- Correcting documented errors or accounting adjustments through formal change control (Correct answer)
- The variance exceeds reporting thresholds
- The CAM wants to improve the cost performance index
Correct answer: Correcting documented errors or accounting adjustments through formal change control
Retroactive changes are limited to correcting errors or routine accounting adjustments and must go through documented change control.
Question 50: A control account's Schedule Performance Index (SPI) is 1.15. What does this indicate?
- The project is 15% over budget
- The project is 15% behind schedule
- The project will complete 15% late
- The project is accomplishing 15% more work than planned for time elapsed (Correct answer)
Correct answer: The project is accomplishing 15% more work than planned for time elapsed
An SPI greater than 1.0 indicates favorable schedule performance; the control account is earning more value than was planned for the period elapsed.
Question 51: What does a risk's 'trigger' or 'warning indicator' represent?
- The person assigned to own the risk
- An early sign that the risk event is about to occur or has occurred (Correct answer)
- The total cost impact of the risk after it happens
- The date the risk is removed from the register
Correct answer: An early sign that the risk event is about to occur or has occurred
A trigger is an observable early-warning condition signaling that the risk is materializing.
Question 52: What is the impact of 'scope creep' on a CAM's resource management?
- It reduces the need for management reserve
- It improves schedule performance by adding work earlier
- It triggers an automatic PMB revision
- It increases resource demand beyond what was planned in the PMB without a corresponding budget or schedule adjustment (Correct answer)
Correct answer: It increases resource demand beyond what was planned in the PMB without a corresponding budget or schedule adjustment
Scope creep adds unauthorized work to a control account, consuming resources not budgeted in the PMB and causing cost and schedule variances without formal change authorization.
Question 53: What is 'make-or-buy analysis' in the context of CAM resource management?
- A comparison of direct vs. indirect labor costs
- A cost-benefit analysis of buying new project management software
- An assessment of whether to use permanent staff or contractors
- An analysis to determine whether to perform work internally or procure it externally (Correct answer)
Correct answer: An analysis to determine whether to perform work internally or procure it externally
Make-or-buy analysis evaluates whether it is more cost-effective and strategically sound to perform work with in-house resources or to outsource it to external vendors.
Question 54: What is 'labor rate variance' in CAM resource management?
- The cost difference between direct and indirect labor
- The difference between planned and actual hours worked
- The variance caused by rework on labor-intensive tasks
- The difference between the planned and actual cost per hour for labor resources (Correct answer)
Correct answer: The difference between the planned and actual cost per hour for labor resources
Labor rate variance measures the difference between the budgeted hourly rate and the actual rate paid for labor, impacting the control account cost performance.
Question 55: Which data management principle is critical in Control Account Manager Certification?
- Keeping all data indefinitely
- Storing data without organization
- Ensuring data integrity, security, and accessibility (Correct answer)
- Only collecting minimal data
Correct answer: Ensuring data integrity, security, and accessibility
Effective data management requires maintaining data integrity, protecting it from unauthorized access, and ensuring it is accessible when needed.
Question 56: A stakeholder asks why the CAM's To-Complete Performance Index (TCPI) of 1.35 matters. The BEST explanation is:
- It means 1.35 staff must be added per month
- It shows the control account is 35% complete
- It indicates a 35% profit margin on remaining work
- It means the team must perform 35% more efficiently than budgeted for all remaining work, which signals the current EAC may be optimistic (Correct answer)
Correct answer: It means the team must perform 35% more efficiently than budgeted for all remaining work, which signals the current EAC may be optimistic
A TCPI well above 1.0 means required future efficiency exceeds past performance, casting doubt on EAC realism.
Question 57: During an Integrated Baseline Review (IBR), what is the CAM primarily expected to demonstrate?
- Ability to negotiate additional management reserve
- Understanding of the scope, schedule, budget, and risks in their control account baseline (Correct answer)
- Authority to change the contract statement of work
- Detailed knowledge of the customer's funding profile
Correct answer: Understanding of the scope, schedule, budget, and risks in their control account baseline
The IBR verifies that CAMs own and understand their baseline, including scope, resources, schedule, and risk.
Question 58: In EVMS, what is 'undistributed budget (UB)'?
- Budget authorized for the project but not yet assigned to specific control accounts or work packages (Correct answer)
- Indirect costs that have not been allocated to control accounts
- The management reserve held outside the PMB
- Budget withheld by the customer pending contract award
Correct answer: Budget authorized for the project but not yet assigned to specific control accounts or work packages
Undistributed budget is budget that has been authorized for the contract but has not yet been formally distributed to specific control accounts or work packages in the WBS.
Question 59: A surveillance auditor finds the CAM's records conflict with the accounting system data. What does this indicate?
- The accounting system should be ignored
- The auditor must accept the CAM's version automatically
- A data integrity and traceability problem that must be reconciled and documented (Correct answer)
- Normal practice, since records never need to match
Correct answer: A data integrity and traceability problem that must be reconciled and documented
EVMS requires traceable, consistent data, so discrepancies between CAM records and the accounting system must be reconciled.
Question 60: Who is responsible for integrating technical, schedule, and cost status into a single monthly assessment of the control account?
- The Control Account Manager (Correct answer)
- The human resources director
- The customer's contracting officer
- The chief financial officer
Correct answer: The Control Account Manager
The CAM owns the integrated technical, schedule, and cost assessment of their control account each reporting period.
Question 61: A Control Account Manager discovers actual costs charged to the wrong control account. What is the appropriate corrective action?
- Leave the charges in place and note the variance in the next report
- Process a documented cost transfer to move the charges to the correct account (Correct answer)
- Use management reserve to offset the misbooked costs
- Adjust the budget in the receiving account to absorb the charges
Correct answer: Process a documented cost transfer to move the charges to the correct account
Misbooked costs must be corrected through a documented, traceable cost transfer, not budget changes or reserves.
Question 62: Which resource management technique assigns resources based on task priority to resolve over-allocation?
- Resource leveling
- Critical chain method (Correct answer)
- Resource crashing
- Resource smoothing
Correct answer: Critical chain method
The critical chain method prioritizes resources to the critical chain (longest resource-constrained path) and uses feeding buffers to protect the project completion date.
Question 63: Under EIA-748, work authorization documents must exist before work begins primarily to ensure that:
- Employees receive overtime pay
- All effort is tied to authorized scope, schedule, and budget with clear responsibility (Correct answer)
- The customer can audit timecards weekly
- Indirect rates remain stable
Correct answer: All effort is tied to authorized scope, schedule, and budget with clear responsibility
Work authorization establishes the formal link between authorized scope, budget, schedule, and the responsible manager before charges begin.
Question 64: Which metric measures the value of work performed in EVM?
- Planned Value (PV)
- Cost Variance (CV)
- Earned Value (EV) (Correct answer)
- Actual Cost (AC)
Correct answer: Earned Value (EV)
Earned Value (EV) is a key metric in EVM that quantifies the value of the work actually performed and completed to date. It represents the budgeted cost of the work performed, indicating how much budget should have been spent for the work accomplished. EV is crucial for assessing the true progress of a project against its plan.
Question 65: What is the purpose of the EVM System Description document that CAMs must follow?
- It records individual salary information
- It replaces the contract statement of work
- It defines the company's documented EVMS processes that CAMs must consistently apply (Correct answer)
- It lists the customer's holiday calendar
Correct answer: It defines the company's documented EVMS processes that CAMs must consistently apply
The System Description documents the company's EVMS processes, and CAM practices must conform to it for compliance.
Question 66: In Control Account Manager Certification practice, what should a professional do when facing a conflict of interest?
- Let someone else decide
- Disclose the conflict and recuse if necessary (Correct answer)
- Ignore it and proceed
- Hide the conflict from others
Correct answer: Disclose the conflict and recuse if necessary
Disclosing conflicts of interest maintains transparency and trust, allowing appropriate action to be taken to prevent bias.
Question 67: In EVMS, what is the significance of 'cost account' versus 'work package'?
- A work package contains multiple control accounts
- A cost account is a summary-level WBS element; a work package is the lowest level where work is planned and controlled (Correct answer)
- A cost account tracks subcontractor costs; a work package tracks direct labor
- Cost accounts are for indirect costs; work packages are for direct costs
Correct answer: A cost account is a summary-level WBS element; a work package is the lowest level where work is planned and controlled
A cost account (control account) is a management control point in the WBS/OBS intersection, while work packages are the lowest-level planning elements containing discrete, measurable tasks.
Question 68: A work package has PV of $60,000, EV of $45,000, and AC of $50,000. What are the cost and schedule variances?
- CV = +$5,000 and SV = +$15,000
- CV = −$10,000 and SV = −$10,000
- CV = −$5,000 and SV = −$15,000 (Correct answer)
- CV = −$15,000 and SV = −$5,000
Correct answer: CV = −$5,000 and SV = −$15,000
CV = EV − AC = −$5,000 and SV = EV − PV = −$15,000, so the package is over cost and behind schedule.
Question 69: Which metric is essential in Control Account Manager Certification stakeholder reports?
- Office supply usage
- Cost Performance Index (CPI) and Schedule Performance Index (SPI) (Correct answer)
- Team headcount only
- Number of meetings held
Correct answer: Cost Performance Index (CPI) and Schedule Performance Index (SPI)
CPI and SPI are critical earned value metrics that show cost and schedule performance at a glance.
Question 70: Apportioned effort is best used for work that:
- Continues at a constant rate regardless of output, such as program management
- Is funded from management reserve
- Has a direct, proportional relationship to a discrete base task, such as inspection of production units (Correct answer)
- Is far-term and not yet planned in detail
Correct answer: Has a direct, proportional relationship to a discrete base task, such as inspection of production units
Apportioned effort earns value in direct proportion to a related discrete base account, fitting tasks like quality inspection tied to production.
Question 71: A CAM assigns Level of Effort (LOE) as the earned value technique for discrete design work to avoid showing schedule variance. Why is this a compliance violation?
- LOE requires customer approval for every use
- LOE may only be used by subcontractors
- LOE automatically earns value with passing time, masking true performance on measurable work (Correct answer)
- LOE always shows a negative schedule variance
Correct answer: LOE automatically earns value with passing time, masking true performance on measurable work
LOE earns value simply by time passing, so applying it to discrete measurable work hides real schedule performance.
Question 72: Which of the following best describes confidentiality in Control Account Manager Certification?
- Keeping all information secret permanently
- Protecting sensitive information from unauthorized disclosure (Correct answer)
- Only sharing information verbally
- Sharing information freely with everyone
Correct answer: Protecting sensitive information from unauthorized disclosure
Confidentiality involves protecting sensitive information and only sharing it with authorized parties who need it.
Question 73: What is the primary purpose of a rolling wave planning approach in control account budgeting?
- Spread management reserve evenly across all periods
- Delay all planning until the customer requests it
- Eliminate the need for work authorization documents
- Detail-plan near-term work while holding far-term budget in planning packages (Correct answer)
Correct answer: Detail-plan near-term work while holding far-term budget in planning packages
Rolling wave planning converts planning packages into detailed work packages as work approaches, keeping plans realistic.
Question 74: During monthly processing, in what order do EVM tool activities generally occur?
- Analyze variances before any data is loaded
- Status the schedule, load actual costs, calculate earned value metrics, then analyze and report (Correct answer)
- Load next month's budget first
- Publish reports, then status the schedule, then load actuals
Correct answer: Status the schedule, load actual costs, calculate earned value metrics, then analyze and report
The monthly rhythm is status inputs first, then calculation, then analysis and reporting.
Question 75: During a review, a customer representative challenges the CAM's percent complete claim on a design work package. What is the CAM's strongest response?
- State that the program manager approved the number so it must stand
- Explain that percent complete is subjective and cannot be verified
- Point to the predefined quantifiable backup data, such as completed drawings versus total planned drawings (Correct answer)
- Agree to change the percent complete to whatever the customer suggests
Correct answer: Point to the predefined quantifiable backup data, such as completed drawings versus total planned drawings
Objective, predefined quantifiable backup data is the CAM's evidence for defending earned value claims.
Question 76: In earned value management, 'Undistributed Budget' (UB) is best described as budget that:
- Has been spent without formal authorization
- Is held in management reserves outside the PMB
- Is part of the PMB but not yet allocated to specific control accounts (Correct answer)
- Has been distributed to specific work packages
Correct answer: Is part of the PMB but not yet allocated to specific control accounts
Undistributed Budget is within the Performance Measurement Baseline but has not yet been assigned to specific control accounts or work packages pending further planning.
Question 77: What distinguishes a planning package from a work package within a control account?
- A planning package has no budget assigned
- A planning package holds far-term budget and scope not yet detail-planned (Correct answer)
- A planning package is used exclusively for material costs
- A planning package contains only management reserve
Correct answer: A planning package holds far-term budget and scope not yet detail-planned
Planning packages hold time-phased budget for far-term scope that will be converted into detailed work packages before work starts.
Question 78: What does an automated log of baseline changes in the EVM tool primarily provide?
- A marketing brochure
- Automatic customer approval
- Faster network speeds
- An audit trail showing when, why, and by whom budgets were changed (Correct answer)
Correct answer: An audit trail showing when, why, and by whom budgets were changed
Change logs create the audit trail required to demonstrate disciplined, documented baseline control.
Question 79: A CAM's control account shows earned value in the cost tool, but the corresponding schedule activities show no status. Which tool discipline was violated?
- Password rotation policy
- Using color coding in reports
- Statusing the schedule and cost system to the same data date (Correct answer)
- Backing up files weekly
Correct answer: Statusing the schedule and cost system to the same data date
Cost and schedule systems must be statused consistently to the same data date so earned value and schedule progress agree.
Question 80: Which document authorizes a CAM to begin work and defines the scope, schedule, and budget of a control account?
- Integrated master plan
- Contract data requirements list
- Work authorization document (Correct answer)
- Responsibility assignment matrix
Correct answer: Work authorization document
The work authorization document formally releases scope, schedule, and budget to the CAM before work begins.
Question 81: What is 'staffing management plan' used for in a CAM's control account?
- To define the project's reporting hierarchy
- To establish individual performance review schedules
- To describe when and how human resource requirements will be met throughout the project (Correct answer)
- To document team training requirements only
Correct answer: To describe when and how human resource requirements will be met throughout the project
The staffing management plan defines when staff will be acquired, how long they are needed, their roles, and release criteria for each phase of the control account.
Question 82: A control account contains material costs that are recorded when items are received, but earned value is claimed when items are installed. What problem does this create?
- No problem, since timing never matters
- A false variance from mismatched timing of actual costs and earned value (Correct answer)
- A violation of the organizational chart
- An automatic improvement in cost performance
Correct answer: A false variance from mismatched timing of actual costs and earned value
Earned value and actual costs for material must be recorded in the same period to avoid artificial variances.
Question 83: A CAM certifying monthly EVM data knowingly containing false performance figures could expose the contractor to liability under which law?
- The Sherman Antitrust Act
- The Lanham Act
- The False Claims Act (Correct answer)
- The Fair Labor Standards Act
Correct answer: The False Claims Act
Knowingly submitting false performance or billing data to the government can create liability under the False Claims Act.
Question 84: What is the purpose of 'Management Reserve (MR)' in an EVMS contract?
- To cover cost overruns identified by the control accounts
- To provide budget held outside the PMB for unplanned in-scope work (Correct answer)
- To supplement overhead and G&A costs during project execution
- To fund approved scope changes from the customer
Correct answer: To provide budget held outside the PMB for unplanned in-scope work
Management Reserve (MR) is budget outside the PMB held by management to address unplanned but in-scope work that arises during project execution.
Question 85: In earned value management, what does the Cost Variance (CV) measure?
- The difference between earned value and actual cost (Correct answer)
- The difference between planned value and actual cost
- The difference between BAC and EAC
- The difference between earned value and planned value
Correct answer: The difference between earned value and actual cost
CV = EV − AC, showing whether work performed cost more or less than budgeted.
Question 86: A control account has BCWS of $200,000 and BCWP of $180,000 at the end of the month. What is the schedule variance (SV)?
- $0
- -$20,000 (Correct answer)
- +$20,000
- -$380,000
Correct answer: -$20,000
SV = BCWP - BCWS = $180,000 - $200,000 = -$20,000, indicating the account is behind schedule.
Question 87: A subcontractor with a $150 million flowdown effort on a DoD program would typically be subject to which EVMS requirement?
- A waiver granted automatically by the prime
- Only quarterly invoice submission
- Exemption because subcontractors never need EVMS
- Flowdown of the EVMS clause requiring a validated, EIA-748-compliant system (Correct answer)
Correct answer: Flowdown of the EVMS clause requiring a validated, EIA-748-compliant system
Primes must flow down EVMS requirements to subcontractors meeting the applicable dollar thresholds.
Question 88: What does informed consent require in Control Account Manager Certification practice?
- Agreement from a third party
- A quick verbal agreement
- Only a signed document
- Full disclosure of relevant information before obtaining agreement (Correct answer)
Correct answer: Full disclosure of relevant information before obtaining agreement
Informed consent requires that all relevant information be provided so the individual can make a knowledgeable and voluntary decision.
Question 89: During an Integrated Baseline Review (IBR), the primary compliance objective is to verify that the:
- Performance Measurement Baseline realistically captures all authorized scope, schedule, and budget (Correct answer)
- Contract has been fully funded by Congress
- Contractor's profit margin is reasonable
- Subcontractors have signed non-disclosure agreements
Correct answer: Performance Measurement Baseline realistically captures all authorized scope, schedule, and budget
An IBR confirms the Performance Measurement Baseline is realistic and covers the entire authorized work scope with adequate resources.
Question 90: Indirect costs applied to a control account are typically controlled by whom?
- The scheduling department
- The CAM, who sets the overhead rates
- The customer's contracting officer
- Managers of the indirect cost pools, not the CAM (Correct answer)
Correct answer: Managers of the indirect cost pools, not the CAM
Indirect rates and pools are managed by functional or pool managers; the CAM manages direct performance.
Question 91: What is the primary risk of 'schedule gaming' in a control account?
- It causes the IMS to become over-resourced
- It distorts the PMB, making earned value metrics unreliable for management decisions (Correct answer)
- It reduces float on non-critical activities
- It increases the cost performance index artificially
Correct answer: It distorts the PMB, making earned value metrics unreliable for management decisions
Schedule gaming — such as claiming unearned value — corrupts the PMB and makes EVM metrics misleading, undermining management's ability to detect real problems.
Question 92: Which scheduling method uses probability-weighted durations (optimistic, most likely, pessimistic) to estimate activity duration?
- Precedence Diagramming Method (PDM)
- Gantt Chart Method
- Critical Path Method (CPM)
- Program Evaluation and Review Technique (PERT) (Correct answer)
Correct answer: Program Evaluation and Review Technique (PERT)
PERT uses three-point estimates — optimistic, most likely, and pessimistic — to calculate a weighted average duration for project activities.
Question 93: Which condition typically triggers an Over-Target Baseline (OTB)?
- The remaining budget is insufficient to realistically plan the remaining work (Correct answer)
- Management reserve exceeds 10% of BAC
- A single month shows an unfavorable schedule variance
- The customer requests a routine progress briefing
Correct answer: The remaining budget is insufficient to realistically plan the remaining work
An OTB reprograms the baseline when remaining budgets are no longer adequate for realistic planning of remaining work.
Question 94: Which skill is most important for success in Advanced Techniques & Methods within Control Account Manager Certification?
- Working without any training
- Avoiding feedback
- Continuous learning and adaptation (Correct answer)
- Resisting change
Correct answer: Continuous learning and adaptation
Continuous learning ensures professionals stay current with evolving practices in Advanced Techniques & Methods.
Question 95: Which report delivers integrated cost and schedule performance data to the government under the current DoD data requirement?
- Contract Funds Status Report only
- DD Form 254
- SF 1408 Preaward Survey
- Integrated Program Management Data and Analysis Report (IPMDAR) (Correct answer)
Correct answer: Integrated Program Management Data and Analysis Report (IPMDAR)
The IPMDAR replaced the legacy IPMR/CPR as the contractual vehicle for delivering EVM performance data.
Question 96: In a CAM's control account, what is 'time-phasing' of budgets?
- Adjusting the schedule baseline after a change order
- Assigning float to near-critical path activities
- Calculating remaining duration for incomplete tasks
- Distributing budget across the project schedule in alignment with planned work (Correct answer)
Correct answer: Distributing budget across the project schedule in alignment with planned work
Time-phasing distributes the budget across the project timeline to reflect when the planned work is expected to be performed, creating the Performance Measurement Baseline (PMB).
Question 97: What is the role of a code of conduct in Control Account Manager Certification practice?
- It only applies to new employees
- It replaces all laws and regulations
- It is optional and rarely enforced
- It establishes expected behavioral and professional standards (Correct answer)
Correct answer: It establishes expected behavioral and professional standards
A code of conduct sets clear expectations for professional behavior, guiding practitioners in their daily activities and decisions.
Question 98: Which statement about Undistributed Budget (UB) is compliant with EIA-748?
- UB is a permanent holding account for contingency funds
- UB holds budget for authorized scope not yet distributed to control accounts and should be allocated promptly (Correct answer)
- UB is identical to management reserve
- UB may be spent directly without allocation
Correct answer: UB holds budget for authorized scope not yet distributed to control accounts and should be allocated promptly
UB is a temporary holding account for authorized but not-yet-distributed scope and budget, which must be distributed in a timely manner.
Question 99: What is the formula for Estimate at Completion (EAC) when current cost performance is expected to continue?
- EAC = BAC − CV
- EAC = AC + BAC
- EAC = AC + (BAC − PV)
- EAC = BAC / CPI (Correct answer)
Correct answer: EAC = BAC / CPI
Dividing BAC by CPI projects total cost assuming the current cost efficiency continues to completion.
Question 100: During integrated baseline review (IBR) preparation, a CAM finds that work package budgets do not sum to the control account budget. What integration principle is violated?
- Vertical traceability of the budget (Correct answer)
- Horizontal schedule logic
- Management reserve allocation
- Rolling wave planning
Correct answer: Vertical traceability of the budget
Vertical traceability requires that work package and planning package budgets sum exactly to the control account total.
Control Account Manager (CAM) Certification
The CAM certification validates expertise in Earned Value Management Systems (EVMS) per the EIA-748 standard, covering organization, planning, scheduling, budgeting, cost control, and performance analysis required of control account managers on government and defense programs.
Exam Rules
- You can skip questions and return to them later
- Flag questions for review before submitting
- No feedback shown until you submit the entire exam
- Unanswered questions count as wrong — answer everything
- 10 pretest questions are mixed in and don't affect your score
- Timer auto-submits when time runs out
- Your progress is auto-saved every 30 seconds