  1. A development team is using threat modeling during the design phase. Which framework is commonly used to categorize software threats?

    Answer: STRIDE

    STRIDE (Spoofing, Tampering, Repudiation, Information Disclosure, Denial of Service, Elevation of Privilege) is Microsoft's threat modeling framework for categorizing software threats.

  2. Which of the following is an example of a secondary risk?

    Answer: A risk that arises as a direct result of implementing a risk response

    Secondary risks are new risks that are created as a direct consequence of implementing a risk response or mitigation strategy.

  3. A CAD candidate must prioritize risks before mitigation. Which tool ranks risks by multiplying their probability and impact scores?

    Answer: Probability-Impact Matrix

    The Probability-Impact Matrix ranks risks by combining their likelihood and consequence scores, creating a visual prioritization grid.

  4. During a risk review meeting, a previously identified risk is found to be no longer relevant to the project. What is the correct action?

    Answer: Close the risk and update the risk register accordingly

    When a risk is no longer applicable, it should be formally closed and the risk register updated to reflect its resolved status.

  5. A software release is blocked by an unresolved risk that has materialized. This materialized risk is now classified as what?

    Answer: An issue

    When a risk actually occurs and becomes a real problem affecting the project, it transitions from a risk to an issue requiring immediate resolution.

  6. Which risk mitigation strategy involves creating multiple independent system components so a single failure does not bring down the entire application?

    Answer: Redundancy and fault isolation

    Redundancy and fault isolation ensure that failures in one component are contained and do not cascade into system-wide failures.

  7. A project manager sets aside 10% of the budget for unforeseen risk events not in the risk register. This reserve is called?

    Answer: Management reserve

    Management reserve is an unplanned budget set aside for unknown-unknown risks outside the identified risk register, controlled by senior management.