Work Study & Methods Engineering Flashcards

7 cards from real BSIE practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Work Study & Methods Engineering flashcards as text
  1. Which technique is used in work study to record all activities performed by an operator or machine on a single chart?

    Answer: Man-machine chart

    A man-machine chart records the simultaneous activities of an operator and machine on a time-scaled chart to identify idle periods.

  2. In time study, the rating factor is used to:

    Answer: Convert observed time to normal time

    The rating factor adjusts observed time to normal time by accounting for the pace of the worker relative to a standard pace.

  3. Which of the following is the correct formula for Standard Time?

    Answer: Normal Time × (1 + Allowance Fraction)

    Standard Time = Normal Time × (1 + Allowance Fraction), where Normal Time = Observed Time × Rating Factor.

  4. A work sampling study is best suited for:

    Answer: Estimating the percentage of time spent on various activities

    Work sampling uses random observations over a period to estimate the proportion of time spent on different activities without continuous observation.

  5. In a Methods-Time Measurement (MTM) system, which basic motion has the shortest normal time?

    Answer: Grasp

    Grasp is generally the shortest basic motion in MTM, as it involves simply closing fingers on an object already in position.

  6. The purpose of a SIMO (Simultaneous Motion) chart is to:

    Answer: Record left-hand and right-hand motions simultaneously at a micro-motion level

    A SIMO chart records the micro-motions of both hands simultaneously using therblig symbols to identify inefficiencies in hand motions.

  7. Which allowance in work study accounts for fatigue, personal needs, and unavoidable delays?

    Answer: PFD allowance

    PFD (Personal, Fatigue, and Delay) allowance is added to normal time to account for worker fatigue, personal time, and unavoidable delays.