← All BE/B Eng Bachelor of Engineering Flashcard Decks

Industrial Engineering Flashcards

7 cards from real BE/B Eng Bachelor of Engineering practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Industrial Engineering flashcards as text
  1. What is the primary objective of linear programming in industrial engineering?

    Answer: To maximize or minimize a linear objective function subject to linear constraints

    Linear programming optimizes (maximizes or minimizes) a linear objective function subject to a set of linear equality or inequality constraints.

  2. In the simplex method for linear programming, the optimal solution always occurs at which location in the feasible region?

    Answer: At a corner point (extreme point/vertex) of the feasible region

    The fundamental theorem of linear programming guarantees that if an optimal solution exists, it occurs at a corner (vertex) of the convex feasible polyhedron.

  3. The Economic Order Quantity (EOQ) model determines the optimal order quantity by minimizing the total of which two costs?

    Answer: Ordering (setup) cost and inventory holding (carrying) cost

    EOQ balances ordering/setup costs (which decrease with larger orders) against inventory holding costs (which increase with larger orders) to find the cost-minimizing quantity.

  4. In PERT/CPM network analysis, the critical path is defined as:

    Answer: The longest path through the network, which determines the minimum project duration

    The critical path is the longest sequence of dependent activities from start to finish; any delay on this path directly delays the entire project.

  5. Time study, a classical work measurement technique, is primarily used to:

    Answer: Establish standard times for performing defined work tasks

    Time study involves observing and timing a qualified worker performing a task at a normal pace, then applying rating factors and allowances to establish a standard time.

  6. In queuing theory, Little's Law states L = λW. What does 'L' represent?

    Answer: The average number of customers in the system (queue + service)

    Little's Law: L (average number of customers in the system) = λ (average arrival rate) × W (average time each customer spends in the system).

  7. Which of the following is NOT one of the seven wastes (Muda) identified in lean/Toyota Production System?

    Answer: Innovation

    The seven TPS wastes are: overproduction, waiting, transportation, over-processing, excess inventory, unnecessary motion, and defects — innovation is not a waste.

Industrial Engineering Flashcards — BE/B Eng Bachelor of Engineering Study Cards with Answers