In a Special Assessment District (SAD), the cost of a public improvement is allocated to property owners based on:
Answer: The proportionate benefit each property receives from the improvement
Special assessments are justified legally only when levied in proportion to the special benefit conferred on each assessed property.
A planner is reviewing a site plan that proposes clearing a riparian buffer. Which federal law most directly governs the discharge of fill material into waters of the United States, including wetlands?
Answer: Section 404 of the Clean Water Act
Section 404 of the Clean Water Act requires a permit from the U.S. Army Corps of Engineers before discharging dredged or fill material into jurisdictional waters.
Which implementation strategy directly ties the timing and phasing of development to the availability of public facilities?
Answer: Growth management and adequate public facilities ordinances
Adequate public facilities ordinances (APFOs) condition development approval on demonstrated capacity in roads, water, sewer, schools, and parks.
A Redevelopment Agency uses eminent domain to assemble parcels for a mixed-use project. The Fifth Amendment requires that taken property be used for:
Answer: A public use with just compensation paid to property owners
The Fifth Amendment's Takings Clause permits government acquisition of private property only for public use and upon payment of just compensation.
Which approach to subdivision regulation requires new subdivisions to be consistent with an official map designating future streets and public spaces?
Answer: Official Map Act
Official map acts authorize municipalities to record a map of planned street rights-of-way and public spaces, preventing conflicting development in those corridors.
A municipality enacts a 'linkage program' requiring large commercial developers to contribute to an affordable housing fund. The legal basis for this requirement rests on:
Answer: The nexus between large employment developments and increased demand for affordable workforce housing
Linkage programs survive legal challenge when a reasonable nexus exists between the development's impacts—such as job creation—and the exaction demanded.
An environmental impact report identifies a significant traffic impact. What is the planner's next required step under typical CEQA or NEPA procedures?
Answer: Identify feasible mitigation measures or alternatives and analyze their effectiveness
Environmental review mandates identification and analysis of feasible mitigation measures or project alternatives that reduce or avoid significant impacts.