โ† All Agile Project Management Flashcard Decks

Estimation Techniques Flashcards

7 cards from real Agile Project Management practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Estimation Techniques flashcards as text
  1. What is the primary purpose of using ideal days as an estimation unit?

    Answer: Estimate work assuming no interruptions or context switching

    Ideal days represent focused, uninterrupted work time, which differs from elapsed calendar time.

  2. Why might a team prefer story points over ideal days?

    Answer: Points avoid implying a specific person's working speed

    Story points abstract away individual speed, making estimates team-shared rather than person-specific.

  3. What is a burndown chart primarily used to show during a sprint?

    Answer: Remaining work over time

    A sprint burndown chart tracks remaining work against time to show progress toward completion.

  4. If a burndown line stays flat for several days mid-sprint, what does it most likely indicate?

    Answer: Work is started but not being completed

    A flat line means no work is being closed out, often a sign of blockers or work-in-progress pileup.

  5. What does a burnup chart add compared to a burndown chart?

    Answer: It separately shows total scope, revealing scope changes

    A burnup chart plots scope as its own line, making scope creep visible alongside progress.

  6. How is remaining capacity typically calculated for sprint planning?

    Answer: Team availability adjusted for time off and non-project work

    Capacity accounts for actual available hours after subtracting leave, meetings, and other commitments.

  7. Why is velocity an empirical metric rather than a target to maximize?

    Answer: Inflating points to raise velocity produces meaningless numbers

    Velocity reflects observed reality; gaming it by inflating estimates destroys its forecasting value.