  1. A user story has acceptance criteria but no clear value to the user. Which INVEST trait is most violated?

    Answer: Valuable

    Every user story should deliver clear value to a user or customer.

  2. What is the recommended response when a single user story is too large to complete in one sprint?

    Answer: Split it into smaller vertical slices

    Large stories (epics) should be split into smaller, independently valuable slices.

  3. In the standard user story template, what is the typical format?

    Answer: As a [role], I want [goal], so that [benefit]

    The 'As a... I want... so that...' format captures role, goal, and benefit.

  4. What is the main role of acceptance criteria attached to a user story?

    Answer: Define the conditions that make the story complete and testable

    Acceptance criteria specify the boundaries and pass/fail conditions for the story.

  5. A team's velocity has been 30, 32, and 28 points over three sprints. What is the most reasonable forecast for the next sprint?

    Answer: Around 30 points based on the average

    Average historical velocity gives a reasonable, sustainable forecast.

  6. What does the 'so that' clause in a user story primarily communicate?

    Answer: The benefit or reason behind the request

    The 'so that' clause expresses the value or motivation for the story.

  7. Which approach helps a new team estimate when they have no velocity history yet?

    Answer: Pick a reference story as a baseline and estimate others relative to it

    Anchoring to a known reference story enables consistent relative estimation from the start.