Scrum Events and Artifacts Flashcards
7 cards from real Agile Project Management practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Scrum Events and Artifacts flashcards as text
What is the time-box for Sprint Planning in a one-month Sprint?
Answer: Eight hours
Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint.
Which topic is NOT addressed during Sprint Planning?
Answer: What process the team should adopt next year
Sprint Planning addresses the why, what, and how of the Sprint, not long-term process strategy.
The Sprint Backlog is a commitment toward which target?
Answer: The Sprint Goal
The Sprint Goal is the single objective the Sprint Backlog commits to.
Who owns the Sprint Backlog?
Answer: The Developers
The Sprint Backlog is a plan by and for the Developers.
What happens to a Product Backlog item that does not meet the Definition of Done at Sprint end?
Answer: It returns to the Product Backlog
Work not meeting the Definition of Done cannot be released and returns to the Product Backlog.
What is the maximum duration of a single Sprint?
Answer: One month or less
Sprints are fixed length events of one month or less to create consistency.
During the Daily Scrum, the Developers may do which of the following?
Answer: Adjust the Sprint Backlog as needed
Developers can adjust the Sprint Backlog at any time, including during the Daily Scrum.