During a sprint review, a key stakeholder disagrees with the product direction.
What should the business analyst do first?
Select your answer
A
Escalate the disagreement to senior management immediately
B
Facilitate a discussion to understand the stakeholder's concerns and capture feedback
C
Override the stakeholder's input since the sprint is already complete
D
Defer all decisions until the next planning session