A concrete finisher is preparing to perform the initial floating of a freshly placed slab.
Which of the following is the primary purpose of bull floating?
Select your answer
A
To create a smooth, dense, hard-troweled surface.
B
To embed large aggregate, level the surface, and remove screed marks.
C
To open the surface to allow bleed water to evaporate quickly.
D
To cut control joints to a depth of one-quarter the slab thickness.