TMP Project & Service Management 2 — Questions and Answers
Question 1: Which ITIL process is responsible for controlling changes to the IT infrastructure to minimize disruption to telecom services?
- Incident Management
- Change Management (Correct answer)
- Problem Management
- Release Management
Correct answer: Change Management
Change Management controls all changes to IT infrastructure to minimize service disruption while enabling necessary improvements.
Question 2: A telecom project manager discovers the project is 15% over budget at the 50% completion mark. Which EVM metric best describes this situation?
- Schedule Variance (SV) is negative
- Cost Performance Index (CPI) is below 1.0 (Correct answer)
- Schedule Performance Index (SPI) is above 1.0
- Budget at Completion (BAC) is exceeded
Correct answer: Cost Performance Index (CPI) is below 1.0
A CPI below 1.0 indicates that for every dollar spent, less than one dollar of work has been accomplished, confirming the over-budget condition.
Question 3: In telecom service management, what is the primary purpose of a Service Level Agreement (SLA)?
- To define the technical architecture of the network
- To document agreed service expectations between provider and customer (Correct answer)
- To establish internal staffing requirements
- To outline vendor procurement procedures
Correct answer: To document agreed service expectations between provider and customer
An SLA formally documents the agreed-upon service levels, metrics, responsibilities, and remedies between a service provider and customer.
Question 4: Which risk response strategy is most appropriate when a telecom project team decides to purchase insurance for equipment damage during deployment?
- Avoid
- Mitigate
- Transfer (Correct answer)
- Accept
Correct answer: Transfer
Purchasing insurance transfers the financial impact of a risk to a third party, which is the Transfer risk response strategy.
Question 5: A telecommunications carrier must restore a major outage within 4 hours per its SLA. This commitment is best described as a:
- Mean Time Between Failures (MTBF)
- Recovery Time Objective (RTO) (Correct answer)
- Recovery Point Objective (RPO)
- Mean Time to Repair (MTTR)
Correct answer: Recovery Time Objective (RTO)
Recovery Time Objective (RTO) defines the maximum acceptable duration of a service outage before restoration must occur.
Question 6: During a telecom network upgrade project, the team identifies that a key vendor will deliver equipment 3 weeks late. This is an example of which type of project dependency?
- Internal finish-to-start dependency
- External dependency (Correct answer)
- Discretionary dependency
- Mandatory dependency
Correct answer: External dependency
An external dependency arises from factors outside the project team's control, such as a vendor's delivery schedule.
Question 7: Which agile ceremony is specifically designed to inspect the increment and adapt the product backlog based on stakeholder feedback?
- Sprint Planning
- Daily Scrum
- Sprint Review (Correct answer)
- Sprint Retrospective
Correct answer: Sprint Review
The Sprint Review is held at the end of each sprint to demonstrate the increment to stakeholders and gather feedback to update the backlog.
Which ITIL process is responsible for controlling changes to the IT infrastructure to minimize disruption to telecom services?