PSI Project and Financial Management 5 — Questions and Answers
Question 1: Which financial concept discounts future cash flows to reflect the time value of money?
- Future Value Analysis
- Net Present Value (NPV) (Correct answer)
- Payback Period
- Benefit-Cost Ratio
Correct answer: Net Present Value (NPV)
NPV discounts all future cash flows back to the present using a required rate of return, reflecting that money today is worth more than money in the future.
Question 2: A project sponsor requests acceleration of the project schedule. The project manager proposes adding more resources to critical path tasks. This is an example of:
- Schedule crashing (Correct answer)
- Fast tracking
- Resource leveling
- Schedule compression through scope reduction
Correct answer: Schedule crashing
Crashing adds resources (people, overtime, equipment) to critical path activities to shorten the schedule, typically at an increased cost.
Question 3: What is the difference between a project constraint and a project assumption?
- Constraints are external; assumptions are internal to the team
- Constraints are known limiting factors; assumptions are considered true without proof (Correct answer)
- Assumptions require approval; constraints do not
- They are functionally identical in project planning
Correct answer: Constraints are known limiting factors; assumptions are considered true without proof
Constraints are known restrictions (budget, time, resources), while assumptions are factors believed to be true but not yet confirmed.
Question 4: Which stakeholder analysis technique maps stakeholders based on their power and interest in the project?
- Risk register
- SWOT analysis
- Power/Interest grid (Correct answer)
- Responsibility assignment matrix
Correct answer: Power/Interest grid
The Power/Interest grid categorizes stakeholders by their level of authority and concern for project outcomes to guide engagement strategies.
Question 5: What is the Internal Rate of Return (IRR)?
- The interest rate charged by the project's lenders
- The discount rate at which a project's NPV equals zero (Correct answer)
- The rate of return required by senior management
- The percentage of budget used at project completion
Correct answer: The discount rate at which a project's NPV equals zero
IRR is the discount rate that makes the net present value of all cash flows from a project equal to zero, used to compare project profitability.
Question 6: A project manager wants to execute two tasks simultaneously to shorten the schedule without adding resources. This technique is called:
- Schedule crashing
- Fast tracking (Correct answer)
- Resource smoothing
- Lead and lag adjustment
Correct answer: Fast tracking
Fast tracking overlaps activities that would normally be done sequentially, compressing the schedule without additional cost but increasing risk.
Question 7: Which document formally records all identified project risks, their probability, impact, and planned responses?
- Risk breakdown structure
- Issue log
- Risk register (Correct answer)
- Assumption log
Correct answer: Risk register
The risk register is the central document capturing identified risks, their analysis results, and assigned risk response strategies.
Which financial concept discounts future cash flows to reflect the time value of money?