Professional Scrum Master Professional Scrum Master Scrum Artifacts and Commitments Questions and Answers 2 — Questions and Answers
Question 1: What is the commitment associated with the Product Backlog?
- Product Goal (Correct answer)
- Sprint Goal
- Definition of Done
- Release Plan
Correct answer: Product Goal
The Product Goal is the commitment for the Product Backlog, giving the team a long-term objective to plan against.
Question 2: A Development Team delivers an Increment that does not meet the Definition of Done. What should the Scrum Master do?
- Coach the team on the importance of transparency and adherence to the Definition of Done (Correct answer)
- Add the incomplete work to the next Sprint automatically
- Report the issue to senior management
- Lower the Definition of Done standards to match the team's output
Correct answer: Coach the team on the importance of transparency and adherence to the Definition of Done
The Scrum Master should coach the team to uphold transparency and quality standards rather than compromise or escalate.
Question 3: Who is accountable for creating a Sprint Backlog that makes the Sprint Goal transparent?
- The Developers (Correct answer)
- The Product Owner
- The Scrum Master
- The entire Scrum Team
Correct answer: The Developers
The Developers own the Sprint Backlog and are accountable for creating a plan that makes progress toward the Sprint Goal visible.
Question 4: During the Sprint, stakeholders request a change to the Definition of Done. What is the correct response?
- The change can be discussed but only adopted at the start of the next Sprint or during Sprint Retrospective (Correct answer)
- The Scrum Master must approve the change immediately
- The Product Owner updates the Definition of Done mid-Sprint
- Changes to the Definition of Done are never allowed
Correct answer: The change can be discussed but only adopted at the start of the next Sprint or during Sprint Retrospective
Changes to the Definition of Done should be deliberated carefully and typically adopted going forward, not retroactively applied mid-Sprint.
Question 5: Which Scrum artifact provides transparency into the work selected for the current Sprint?
- Sprint Backlog (Correct answer)
- Product Backlog
- Increment
- Burndown Chart
Correct answer: Sprint Backlog
The Sprint Backlog provides transparency into all the work the Developers identify as necessary to meet the Sprint Goal.
Question 6: What happens if the Sprint Goal becomes obsolete during a Sprint?
- The Product Owner can cancel the Sprint (Correct answer)
- The Developers remove the Sprint Goal and continue working
- The Scrum Master extends the Sprint to accommodate changes
- The team votes on whether to continue
Correct answer: The Product Owner can cancel the Sprint
Only the Product Owner has the authority to cancel a Sprint, and an obsolete Sprint Goal is a valid reason to do so.
What is the commitment associated with the Product Backlog?